Title Page
-
Contractor name
-
RTIO Operating Site / Project Manager
-
Scope of works
-
Conducted on
-
Intended de-mob date
-
Completed by
-
Waste Management
Area
-
Area description
-
Have all surplus construction materials not intended for operations been removed from site?
-
Is the area free from litter, particularly food scraps, survey pegs, flagging and cigarette butts?
-
Have oil drums or other chemical storage devices been removed offsite?
-
Has plastic lining been removed from secondary containment bunds and disposed of appropriately?
-
Has contaminated soil been dug out and disposed of offsite?
-
Has spoil material been removed off site or been appropriately stockpiled in designated location as instructed by RT?
-
Have samples of suspects contaminated areas been conducted as instructed and sampling results provided to the RT Environmental Advisor? HC's, Septic, chemical etc
-
Has wastewater (I.e. Sewage, grey water) been disposed of to a designated location or removed off-site by an appropriate waste removal provider?
-
Landscaping and Rehabilitation
Area
-
Area description
-
Have sumps, pits, trenches and other excavation type temporary installations been back filled and rehabilitated?
-
Have all temporary infrastructure been removed (eg crib huts, concrete foundations / slabs, blue metal, above ground services, etc) and removed from site?