Information

  • Inspection Title

  • Document No.

Project Information

  • Client / Site

  • Conducted on

  • Prepared By

  • Prepared by Other:

  • Location
  • Building

  • Floor Level

  • Room or Space Number

HEALTH & SAFETY

  • JHA prepared for work

  • Is the area free of hazards (trip hazards, struck-by, fall hazards, etc.)

  • Are workers wearing proper PPE

  • Scaffold in use

  • Scaffold daily tag completed and approved for use

QUALITY ASSURANCE

  • Are all QC Forms Completed by Contractor

  • First Delivery Form Completed

  • Definable Features of Work Form Completed

  • Submittals on File

  • Status of submittals on file

  • Any issue with Submittals

  • Materials or Equipment Stored in conformance to contract

  • Insert picture of area/materials/equipment

MATERIAL/PLANT

  • Is the approved masonry being used

  • Three hour rated CMU

  • Two hour rated CMU

  • Non rated CMU (grey block)

  • Split face CMU

  • Brick (Type 1)

  • Brick (Type 2)

  • Precast Unit

  • Masonry Unit being inspected

  • Is the approved mortar being used

  • Type 'S'

  • Mortar being inspected

  • Is the mortar being tooled properly (V Joints at exposed joints and Concave at concealed joints)

  • Is reinforcement being placed per contract

  • Horizontal and vertical reinforcement bars

  • Rebar being inspected

  • Horizontal mortar bed reinforcement

  • Horizontal mortar bed reinforcement being inspected

  • Anchors and ties

  • Anchor ties being inspected

  • Is the approved mortar net being used

  • Is the approved weep vents being used

  • Will Non-compliance Notice be issued for any work noted above

LABOR RESOURCES (refer to Daily Field Report for workforce summary)

  • Do we have sufficient Labor to Complete Installation per Schedule

SUGGESTIONS FOR IMPROVEMENT

  • Take Photo of Areas for Improvement

  • Insert Areas For Improvement

  • Insert Suggestions To Improve installation

INSPECTION CARRIED OUT BY

  • Signed

  • Select date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.