Stored Materials
-
Are materials stacked and stored to prevent weathering and warping?
-
Are materials stacked according to OSHA guidelines?
-
Are materials staged on solid surface to avoid tilting and rocking?
Walls Interior and Exterior
-
Are interior walls plumb?
-
Is required blocking for fire/mounting/nailing installed per plan?
-
Are all blocking and backing flush with face of framing?
-
Are walls squared?
-
Are correct headers installed for load bearing walls/ non load bearing walls?
-
Are correct amount of kings and cripple studs installed?
-
Are sheer walls sheeted and nailed off according to schedule?
-
Is weather barrier installed and fastened to withstand weather and wind?
-
Are walls free of brace blocks and nails?
-
Are walls fastened to substrate with correct fasteners?
-
Are all required brackets/holddowns/anchors installed per plan and schedule?
-
Do all hold down posts match required schedule for ply size?
Floor System
-
Has layout been verified?
-
Are correct hanger brackets used for floor system?
-
Are the correct floor joists series installed per plan?
-
Do all joists meet minimum bearing depth?
-
Is all rim board installed to support joists?
-
Are joist toe nailed to plates?
-
Are hold down clips installed per plan?
Rafter System
-
Has rafter layout been verified?
-
Are rafter installed per plan?
-
Are lateral braces installed per plan?
-
Are correct hanger and hold down clips installed per schedule and rafter plan?
-
Are rafter cords and members free of splits and cracks?
-
Are press plate seated with out kinks and bends?
Ceilings
-
Are joists the correct size per plan?
-
Are joist hangers installed according to plan and materials used?
-
Are joists confirmed to be under span?
-
Are joists crowned all the same direction?
-
Are ceilings framed flat and level?
-
Is ceiling framing clear of bracing and nails?