Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

1. Policy

  • 1. Policy being displayed

  • 2. Policy being communicated

2. Scheduled Waste Management

  • 1. Notification of Scheduled Waste generation to DOE

  • 2. Proper storage area

  • 3. Updated inventory list

  • 4. Proper labelling & coding

  • 5. Scheduled Waste collector & facility provider are registered and approved by DOE

  • 6. Disposal of Schedule Waste as per requirement (Not more than 180 days / not more than 20 tonne from the date generation)

  • 7. Consignment notes availability

3. Solid Waste Management

  • 1. Domestic Waste is managed properly at site

  • 2. Construction Waste is managed properly at site

  • 3. Domestic Waste is managed properly at Kongsi

  • 4. Designated area for Solid Waste

  • 5. Approved Solid Waste collector by Local Authorities

  • 6. No traced of open burning

4. Spillage Control

  • 1. Sufficient containment bund is provided for concrete mixer, bar bending machine & generator set

  • 2. Maintenance of Vehicles/Machinery

  • 3. Chemical Spillage

5. Erosion & Sediment Control

  • 1. Silt Trap/Retention Pond/Sediment Basin located at the lowest point

  • 2. ESCP constructed as per approved & endorsed drawings

  • 3. Silt trap is properly maintain

  • 4. Geotextile used for gabions and silt traps in good condition

  • 5. Perimeter drain constructed along Project boundary

  • 6. Slopes are properly protected (i.e compacted, turfed, plastic sheet)

  • 7. Earth stockpiled protected by plastic sheet

  • 8. Silt fence properly installed and maintained

  • 9. Wash through facilities provided at exit point and effectively functioned

  • 10. Water browser deployed

  • 11. Drainage system cleared of sedimentation

  • 12. Sewage and sullage discharge not channel to silt trap

  • 13. Proper installation and maintenance of check dams

  • 14. Access road is properly maintained

6. Sewerage and Sullage Control

  • 1. Sewerage is managed properly at site

  • 2. Sullage is manage properly at site

  • 3. Sewerage is managed properly at kongsi

  • 4. Sullage is managed properly at kongsi

7. Environmental Mitigation Measure

  • 1. Wash through

  • 2. Road/access maintenance

8. Personal Protective Equipment

  • 1. Safety Boots

  • 2. Safety Helmet

  • 3. Safety Harness

  • 4. Hand protection

  • 5. Other PPE (face shield, hearing protection, dust mask, safety vest)

9. Scaffolding

  • 1. Competent Erector and inspector

  • 2. Tagging System

  • 3. Inspection Checklist

  • 4. Endorsed design

  • 5. Scaffold erected as per endorsed drawing (platform, railing, cross brace, wall tie, access, base)

  • 6. Condition of scaffold

10. Form Work/False Work

  • 1. Calculation & design by PE

  • 2. Inspection by competent person

11. Working at Height

  • 1. Proper working platform

  • 2. Proper access/staircase

  • 3. Proper PPE (harness, safety Shoe, helmet)

  • 4. Supervision

  • 5. Permit to Work System

12. Hot Work

  • 1. Permit To Work System

  • 2. Fire Extinguisher Provided

13. Hard Barricade

  • 1. Exposed edges, floor opening and lift core barricaded

  • 2. Barricade or cover are firm

  • 3. Staircase have railings

  • 4. Warning sign

14. Excavation

  • 1. Barricade around excavated area

  • 2. Adequate protection electrical installation

  • 3. Proper access and ingress

  • 4. Warning sign

  • 5. Permit to Work system

15. Electrical Safety

  • 1. Warning sign

  • 2. Proper electrical installation

  • 3. Responsible person

  • 4. Electrical wire not laid in ground

  • 5. Portable tools inspected and certified safe

16. Certificate of Fitness

  • 1. Air compressor

  • 2. Crane

  • 3. Competent Operator

  • 4. Crane maintenance record

  • 5. Passanger hoist

  • 6. Passenger hoist maintenance record

  • 7. Training records

  • 8. Inspection record

17. Housekeeping

  • 1. Work area

  • 2. Canteen area

  • 3. Kongsi Area

18. Emergency Preparedness & response

  • 1. Available & displayed ERT Chart

  • 2. Available & displayed Emergency Escape Route

  • 3. Fire Fighting Equipment

  • 4. First Aid Facilities

  • 5. Assembly area

  • 6. Emergency contact number displayed

  • 7. Emergency and evacuation drill conducted

19. Confined Space

  • 1. Warning sign

  • 2. Permit to Work system

  • 3. Competent Person

  • 4. Supervision and Standby Person

20. General Requirement

  • 1. Site registration with DOSH

  • 2. Availability of qualified SHO/Safety Supervisor and designated Environmental Officer

  • 3. CIDB Green Card availability

  • 4. Adequate display of ESH signage's, notices, info i.e. Safety First, Safety reminder, Wearing of Suitable PPE, dangerous/harmful chemical and flammable material

  • 5. Safe access & egress

  • 6. Adequate lighting

  • 7. Adequate toilet facility

  • 8. Water ponding

  • 9. Availability & displayed Safety Committee chart

  • 10. Appointment letter & minute of meeting

21. SDP Requirement

  • 1. Approved SHMP

  • 2. Approved EMP

  • 3. ESH Inspection Checklist

  • 4. Water quality monitoring within stipulated limit (EIA Approval Condition)

  • 5. Air quality monitoring within stipulated limit (EIA Approval Condition)

  • 6. Noise monitoring within stipulated limit (EIA Approval Condition)

  • 7. Written notice from Department Of Environment for installation of diesel Powered power Generator. (More than 110 KVA)

Other non compliance

  • Other non compliance issues

Corrective Action Request (CAR)

  • Deadline for submission of Corrective Action

Other Comments

  • Other comments

  • On site representative

  • Consultant/SDP Technical Supervisor

  • SDP ESH Representative

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.