Title Page

  • Inspection Title

  • Site

  • Conducted on

  • Prepared by

  • Location

1. Policy

  • 1. Policy being displayed

Scheduled Waste Management

  • 1. Notification of Scheduled Waste generation to DOE

  • 2. Proper storage area

  • 3. Updated inventory list

  • 4. Proper labelling & coding

  • 5. Scheduled Waste collector & facility provider are registered<br>and approved by DOE

  • 6. Disposal of Schedule Waste as per requirement (Not more than 180 days / not more than 20 tonne from the date generation)

  • 7. Consignment notes availability

Solid Waste Management

  • 1. Domestic Waste is managed properly at site

  • 2. Construction Waste is managed properly at site

  • 3. Domestic Waste is managed properly at Kongsi

  • 4. Designated area for Solid Waste

  • 5. Approved Solid Waste collector by Local Authorities

  • 6. No traced of open burning

Spillage Management

  • 1. Sufficient containment bund is provided for concrete mixer,<br>bar bending machine & generator set

  • 2. Proper Maintenance of Vehicles/Machinery

  • 3. Chemical Spillage

Erosion & Sediment Control Component

  • 1. Silt Trap/Retention Pond/Sediment Basin located at the<br>lowest point

  • 2. ESCP constructed as per approved & endorsed drawings

  • 3. Silt trap is properly maintain

  • 4. Geotextile used for gabions and silt traps in good conditions

  • 5. Perimeter drain constructed along Project boundary

  • 6. Slopes are properly protected (i.e compacted, turfed, plastic<br>sheet)

  • 7. Earth stockpiled protected by plastic sheet

  • 8. Silt fence properly installed and maintained

  • 9. Wash trough facilities provided at exit point and effectively<br>functioned

  • 10. Water browser deployed

  • 11. Drainage system cleared of sedimentation

  • 12. Sewage and sullage discharge not channel to silt trap

  • 13. Proper installation and maintenance of check dams

  • 14. Access road is properly maintained

Environmental Monitoring

  • 1. Conducted as per EIA Approval Conditions

  • 2. Water, Air and Noise (and vibration) are within stipulated<br>limit

  • 3. No sullage or sewage effluent should be discharged into sediment pond or directly into any rivers or public area before it is adequately treated.

Personal Protective Equipment

  • 1. Safety Boots

  • 2. Safety Helmet

  • 3. Safety Harness

  • 4. Hand protection

  • 5. Other PPE (face shield, hearing protection, dust mask,<br>safety vest)

Scaffolding

  • 1. Competent erector and inspector

  • 2. Tagging system

  • 3. Inspection checklist

  • 4. Endorsed design

  • 5. Scaffold erected as per endorsed drawing<br>(platform, railing, cross brace, wall tie, access, base)

  • 6. Conditions of scaffold

Form Work/ False Work

  • 1. Calculation & design by PE

  • 2. Inspection by competent person

Working At Height

  • 1. Proper working platform

  • 2. Proper access/staircase

  • 3. Proper PPE (harness, safety Shoe, helmet)

  • 4. Supervision

  • 5. Permit to Work System

Hard Barricaded

  • 1. Exposed edges, floor opening and lift core barricaded

  • 2. Barricade or cover are firm

  • 3. Staircase have railings

  • 4. Warning sign

Excavation

  • 1. Barricade around excavated area

  • 2. Adequate protection (shoring, sheetpile, staging)

  • 3. Proper access and ingress

  • 4. Warning sign

  • 5. Permit to Work system

Electrical System

  • 1. Warning sign

  • 2. Appropriate electrical installation

  • 3. Responsible person

  • 4. Electrical cable not laid on ground

  • 5. Portable tools inspected and certified safe

Certificate of Fitness

  • 1. Air compressor

  • 2. Crane

  • 3. Competent operator

  • 4. Crane maintenance record

  • 5. Passenger hoist

  • 6. Passenger hoist maintenance record

  • 7. Training records

  • 8. Inspection records

Housekeeping/ Cleanliness

  • 1. Work area

  • 2. Canteen area

  • 3. Workers Quarters Area

Emergency Preparedness & Response

  • 1. Availability & displayed of ERT Chart

  • 2. Availability & displayed of Emergency Escape Route

  • 3. Fire Fighting Equipment

  • 4. First Aid facilities

  • 5. Assembly area

  • 6. Emergency contact number

  • 7. Emergency and evacuation drill conducted

  • 8. Vehicles emergency stop

Confined Space

  • 1. Warning sign

  • 2. Permit to Work system

  • 3. Competent Person

  • 4. Supervision and Standby Person

Ladder

  • 1. Use of wooden ladder is not allowed

General Requirement

  • 1. Site registration with DOSH

  • 2. Availability of qualified SHO/Safety Supervisor and designated Environmental Officer

  • 3. CIDB Green Card availability

  • 4. Adequate display of ESH signages, notices, info

  • 5. Safe access & egress

  • 6. Adequate lighting

  • 7. Adequate toilet facility

  • 8. Water ponding

  • 9. Cleanliness of workers quarters

SDP Requirement

  • 1. Approved SHMP

  • 2. Approved EMP

  • 3. ESH Inspection Checklist

  • 4. Green zone components are adequate

  • 5. Turnstile / access system is effectively functional

  • 6. Traffic management (signage, signalman)

Other Comment Non Compliance

  • Other Non Compliance issues

Other Comments

  • Other Comments

  • Contractor Reps

  • Consultant / SDP Reps

  • SDP ESH Rep

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.