Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Section 1: Planning
-
1.1 Did the Additive Operator have the additive transported to the site in a safe manner?
-
1.2 Did the Additive Operator conduct a risk assessment if the operation was to be conducted under pressure?
-
1.3 Did the Additive Operator hold a safety meeting with relevant ship and/or shore personnel before any operations were carried our?
-
1.4 Did the Additive Operator complete a safety checklist?
-
1.5 If the cargo treatment was carried out on board a ship, were the hazardous areas clearly identified?
-
1.6 Was the Additive Operators dose rate based on a laboratory bench blend?
Section 2:HSE
-
2.1 Was the additive operator wearing PPE appropriate to task?
-
2.2 Did the additive operator have an MSDS For the cargo being treated?
-
2.3 Did the additive operator have an MSDS for the additive used to treat the cargo?
-
2.4 Was the additive operator fully aware of all hazards referred to in the MSDS?
-
2.5 If any sampling was undertaken, was it performed in accordance with industry guidelines?
Section 3: Equipment
-
3.1 Was the equipment tagged to show that it had been recently safety checked?
-
3.2 Could the additive company provide certificates to show equipment compliance?
-
3.3 Was the equipment certified for use in a hydrocarbon rich environment?
-
3.4 Was the additive operators equipment compatible with the additives chemistry?
-
3.5 Were joints and/or couplings custom made?
-
3.6 Did the additive operator ensure that the additive site would be effective for the treatment of the cargo?
-
3.7 Were all hoses containing high pressure fluids or air in good working condition?
-
3.8 If the cargo is being treated via the manifold, did the additive operator monitor the load/discharge rate to ensure the correct dosage rate?
Section 4: Communications
-
4.1 Were copies of the MSDS distributed to the appropriate vessel and shore personnel?
-
4.2 Did the additive operator obtain the appropriate clearances to operate equipment on site?
-
4.3 Did the subcontracted additive operator complete and send on form to principal additive operator?
-
4.4 Did the additive operator report any unusual or unsafe practice?
-
4.5 Did the additive operator seek approval prior to any open cargo treatment?
-
4.6 Did the additive operator send the BP operator a time log and explain any delays sufficiently?
-
4.7 Did the additive operator submit a field report detailing findings and anomalies?
Section 5: Any Other comments and Observations
-
Cargo Assurance