General Details
-
Site conducted
-
Job
-
Date
-
Asset Number
-
Engineer
Condenser Unit Checks
-
Full Load Amps (From data plate)
-
Compressor MCB Size
-
Contactor Size
-
Overload Setting (FLA + 10%)
-
Is the Compressor Three Phase?
-
Compressor Running Amps
-
Voltage Check Between Live & Neutral
-
Running Amps Phase 1
-
Running Amps Phase 2
-
Running Amps Phase 3
-
Voltage Check Between Phases
-
Compressor Oil Level
-
Operation of Oil Switch Tested
-
Oil Separator Installed
-
Oil Return to Compressor Visible
-
Oil Return Solenoid Working Correctly
-
Condenser Fan Operating Correctly
-
Low Pressure Control Working
-
High Pressure Control Working
-
PRV Setting Higher Than High Pressure Control
-
Liquid Line Solenoid Valve Working Correctly
-
Does Compressor Pump Down Successfully
Evaporator Checks
-
Full Fan Load
-
Fans MCB Size
-
Fan Contactor Size
-
Fan Overload Setting (FLA + 10%)
-
Defrost Heater MCB Size
-
Defrost Heater Contactor Size
-
Is The Heater Supply Three Phase
-
Amps Phase 1
-
Amps Phase 2
-
Amps Phase 3
-
Total Amps
-
Drain Pipe Installed Correctly
-
Heater Tape Working
Refrigeration Pipework Checks
-
Pipework Strength Test Passed
-
Pipework Leak Test Passed
-
Pipework Vacuum Test Passed
-
Pipework Lagged and Secure
Refrigerant Checks
-
Refrigerant Type
-
System Fully Charged
-
Sightglass Indicator Dry
-
System Superheat Within Acceptable Limits
-
F-Gas Label Fitted
Notes
-
Note Required
-
Note
Pictures
-
Picture