Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
RACK INSTALLATIONS
-
Rack installed as per floor plan.
-
Earth bar relocated to bottom of rack.
-
Isolation requirements met:<br>
-
35mm spacing between any other rack and wall
-
270mm from rear of wall ( unistrut mounted to achieve this)
-
Top bracket installed with isolation achieved.<br>
-
35mm earth from earth bar to SPC.
-
Rack labelled as per Telstra standard.
-
2nd and 3rd rack installed with isolation achieved.<br>
RBS 6202 INSTALLATION
-
RBS a installed in rack as per design layout.
-
4 RU spacing a left above RBS for fan unit.
-
All 10 x captive nuts used to install RBS.
-
RBS support brackets removed to free up space.
-
35mm earth cable connected to earth point on left hand side using flat and spring washers provided.
-
35mm earth ran from RBS to rack earth bar.
-
35mm power cable ran on left hand side.
-
Power and earth cable do not impede access to fan units.
-
125A CB used.
-
Correct connections used to connect to power systems and covered in heat shrink.
-
Cables labelled at both ends and covered in clear heat shrink.<br>
-
DC CB legend updated.
FILTER / COMBINER INSTALLATION
-
Filters and Combiners positioned in rack as per layout.
-
Tails formed in neatly.
-
RF connectors torqued to 28 or 25Nm as per manufactures instructions.
-
Feeders labelled including Feeder Opening Point labels.
-
Combiner labels to be in plastic pouches and fitted towards the bottom ( below the securing rail).
SIU-02
-
SIU-02 is powered from DC power system and fed from 6A CB.
-
Cable guide installed below SIU-02.
FIBRE'S
-
All fibres ran in corrugated conduit and fastened to overhead cable tray.
-
MPO cassette patch panels installed where fibre are not l one enough to reach new rack.
-
There is enough slacking the MTP patch cables to pull the patch tray forward.
-
MTP patch panels labelled.
-
Fibre conduits routed down right hand side of the racks.
-
Excess fibre stored in fibre management trays.
GPS INSTALLATION
-
GPS installed in correct position as per FC drawings / design.
-
GPS is separated from any mobiles antenna by 2m.<br>
-
Surge arrestor mounted in horizontal fashion close to gland window.
-
Surge arrestor is left 'floating'.
-
Surge arrestor earthed back to FEB using 35mm earth in conduit.<br>
-
Earth cable is labelled at both ends.
-
RF cable bridproofed and labelled.
-
If the RF cable is greater than 5m than the GPS antenna is earthed back to FEB with 35mm earth cable, bridproofed and labelled.
-
4 way GPS splitter mounted close to height of first row of Combiners.
-
GPS receiver mounted close to second row of Combiners.
-
GPS splitter and receiver connected together using SMA cables.
-
All SMA cables labelled.
-
GPS receiver cables connected to RBS 6202 in correct sequence.
-
All GPS cables labelled.