Antenna Installation
-
Correct antennas installed as per SBD?
-
Antennas installed in correct position as per FC drawings?<br>
-
RF hazard stickers installed on back of all antennas?
-
Orientation, mechanical and electrical tilts as per design?
-
Antenna ports weatherproofed?
-
All brackets tightened?
MHA's and Combiners Installation
-
MHA's / Combiners installed the correct way up?
-
All ports weatherproofed?
-
MHA's / Combiners earthed using 35mm earth.
-
Equipment securely fixed to steelwork?
RRU Installation
-
RRU's installed in correct position as per FC drawings?
-
RRU's installed using correct fixing method?
-
RRU's earthed using 35mm earth?
-
Are covers installed and fixed with a S/S cable tie?
-
All weatherproofing gromets in place?
-
All ports weatherproofed?
-
Plumbed correctly as per plumbing diagram?
-
All cables labelled correctly?
Hybrid Feeders and Jumpers
-
Hybrid jumpers birdproofed?
-
Jumpers connected into the correct ports?
-
Trunk and jumper cables labelled?
-
Junction box and trunk cable earthed?
-
Trunk and jumper cables secured?
Feeders / Trunk Cables
-
Correct type of feeders installed as per SPD?
-
Feeders earthed?
-
Moisture block fitted?
-
Feeders fixed using the correct fixing method?
-
All connectors tight and weatherproofed?
-
Correct size gland used and tightened?
-
Feeders not in contact with any sharp edges?
-
Feeders are labelled correctly?
-
Feeders run is neat and tidy?
Steelwork
-
Steelwork installed as per FC drawings?
-
Steelwork is earthed back to earth ring?
-
All nuts and bolts are tight. Double nutted where necessary?
-
No sharp edges / cuts?
-
All cuts / drill holes been cold - galled?
-
Cable trays installed as per design?
-
Cable trays earthed?
-
Steelwork painted where necessary?
-
Plinths grouted and coated in a water proof membrane.