Title Page

  • Project Number

  • Location
  • Network

  • Feeder number

  • Conducted on

  • Task
  • Task Description

  • Is the task Rail work related?

  • 'All works are to comply with the VicTrack Network Protection Plan TS-SP-015'

  • PPE to be Utilised

  • List other PPE required

  • Prepared by

1. HRCW on or adjacent to roadways or railways used by road or rail traffic

1. HRCW on or adjacent to roadways or railways used by road or rail traffic

  • Working adjacent to road or rail in the vicinity of traffic

Hazard/Risks

  • Vehicle / Rail Traffic / mobile plant movement

  • VERIFICATION - TMP no:

  • VERIFICATION - Worksite compliant with TMP

Hazard/Risks

  • Personnel, contractors & the general public being struck by vehicles

  • VERIFICATION - Warning lights on all plant/vehicles

  • VERIFICATION - Where is the nominated evacuation location/area

  • Plant and Equipment being struck by vehicles

  • Fires (grass)

  • Members of the public or animals distracting and or threatening Prasinus personnel’s safety

  • Uneven/slippery ground or surfaces causing slip, trip, fall hazards

  • Environmental Damage

  • Are there other hazards present?

  • Other Hazards
  • Additional Hazards / Risks:

  • Additional controls and implementation:

  • Photos

2. HRCW at workplaces where there is any movement of powered mobile plant

2. HRCW at workplaces where there is any movement of powered mobile plant

  • Plant set up and operation

  • Select all that apply:

  • List other plant

Hazard/Risks

  • Plant and equipment failure

  • VERIFICATION - Plant pre-start completed

  • VERIFICATION - Logbook Completed

  • VERIFICATION - Crane checklist completed

  • • Electrical shock from plant • Flash over between mobile plant

  • VERIFICATION - Earth required

  • VERIFICATION - Permit #

  • Personnel struck by plant

  • Vehicle Roll Away

  • Unstable/ uneven/ slippery ground conditions

  • Plant collapse/ roll over

  • Crush injuries

  • Uncontrolled release of suspended load

  • • Working beneath suspended loads • Dropped objects

  • • Struck by object/ uncontrolled load • Mobile Plant Operating at height

  • Contacting Conductors

  • Are there other hazards/risks present?

  • Other Hazards
  • Additional Hazards / Risks:

  • Additional controls and implementation:

  • Photos

3. HRCW where there is a risk of a person falling more than two metres

3. HRCW where there is a risk of a person falling more than two metres

  • Working above 2 metres

  • Select all that apply

Hazard/Risks

  • Fall from mobile plant or ladder

  • VERIFICATION - Pole strap/Harness/Lanyards checked prior to use (within inspection date)

  • Pole collapse

  • VERIFICATION - Safe to climb test performed

  • Equipment/Plant failure

  • VERIFICATION - Ladders checked prior to use (within inspection date)

  • Dropped objects

  • VERIFICATION - Exclusion zone has been delineated

  • VERIFICATION - Exclusion zone area in metres

  • VERIFICATION - What is the area in metres

  • VERIFICATION - What method of exclusion zone delineation

  • Reason Why

  • VERIFICATION - EWP has X-arm holding straps fitted and being used

  • Are there other Hazards/Risks

  • Other Hazards
  • Additional Hazards/Risks:

  • Additional controls and implementation:

  • Photos

4. HRCW at workplace where structural alterations that require temporary support to prevent collapse

4. HRCW at workplace where structural alterations that require temporary support to prevent collapse

  • Working on or adjacent to a Pole/Structure

  • Select all that apply

Hazard/Risk

  • • Hardware failure • Unplanned outage • Public Injury

  • VERIFICATION - Structure(s) has been assessed prior to being removed

  • Personal injury (Manual handling)

  • Persons/vehicles struck by collapsing pole/structure

  • VERIFICATION - Exclusion zone has been delineated

  • VERIFICATION - Exclusion zone area in meters

  • VERIFICATION - Exclusion zone area in meters

  • VERIFICATION - What method of exclusion zone delineation being used - Barrier type:

  • Reason Why

  • VERIFICATION - Support Method

  • Are there other hazards/risks

  • Other Hazards
  • Additional Hazards/Risks

  • Additional controls and implementation

  • Photos

5. HRCW on or near energised electrical installations or services

5. HRCW on or near energised electrical installations or services

5a. Working adjacent to LV and HV electrical installations

  • Working adjacent to LV and HV electrical installations

Hazard/Risk

  • - Uncontrolled contact with live assets - Electrocution - Wrong circuit - Unplanned outage - Hardware failure - Death, Injury - Injury to public

  • Are there other hazards/risks

  • Other Hazards/Risks
  • Additional Hazards/Risks

  • Additional controls and implementation

  • Photos

5b. LV - Working on (live) or near electrical installation

  • LV - Working on (live) or near electrical installation

Hazard/Risk

  • - Electrocution - Wrong circuit - Unplanned outage - Hardware failure - Death, Injury - Injury to public

  • De-energise Site controls required to be implemented

  • LV circuit is to remain energised site controls required to be implemented

  • VERIFICATION - All operating equipment, including insulated mats, covers and PPE have been inspected prior to use and in test date

  • Site controls required to be implemented

  • VERIFICATION - EAP/LVIBS/SFT/PTW/SILV Number

  • VERIFICATION - What is the number

  • Are there other hazards/risks

  • Other Hazards/Risks
  • Additional Hazards/Risks

  • Additional controls and implementation

  • Photos

5c. HV working on or near electrical installation HV

  • HV working on or near electrical installation HV

Hazard/Risk

  • - Electrocution - Wrong circuit - Unplanned outage - Hardware failure - Death, Injury - Injury to public

  • Site Controls required to be implemented

  • VERIFICATION - EAP/LVIBS/SFT/PTW/SILV/Live Line Sequence Number

  • VERIFICATION - Enter the number

  • VERIFICATION - Are insulated mats and covers required

  • VERIFICATION - Have they been applied

  • VERIFICATION - Live Line Sequence / Auto Reclose (HV only)

  • De-energise HV electrical circuit Site controls required to be implemented

  • VERIFICATION - Ensure all personnel are clear of the line

  • VERIFICATION - All personnel have signed off applicable permits

  • VERIFICATION - All controls met in accordance with Green Book and Network operational requirements

  • HV Circuit is to remain energised site controls required to be implemented

  • VERIFICATION - All operating equipment and PPE have been inspected prior to use and in test date

  • Are there other hazards present

  • Other Hazards/Risks
  • Additional Hazards/Risks

  • Additional Controls and implementation

  • Photos

6. HRCW involving a trench or shaft if the excavated depth is more than 1.5 metres

6. HRCW involving a trench or shaft if the excavated depth is more than 1.5 metres

  • Excavating/backfilling of trench/shaft

  • Select all that apply

Hazard/Risk

  • - Underground assets damage - Striking underground assets

  • VERIFICATION - DBYD sequence number

  • VERIFICATION - Date on DBYD enquiry/request

  • VERIFICATION - Assets confirmed and proved

  • VERIFICATION - Method of non-invasive excavation

  • Trench/Pole Hole excavation collapse

  • VERIFICATION - Excavation has been benched/shored

  • VERIFICATION - Open Excavation Safety Observer(s)

  • Name

  • People proximity to excavation equipment

  • VERIFICATION - Designated entry/exit into trench

  • - Falls into shafts/trenches - Plant and equipment falling into open excavation

  • Entanglement in auger and plant

  • Dust inhalation Concrete etc

  • VERIFICATION - P2 Masks available and worn on site

  • - Electrocution - Unplanned power outage

  • - Environmental damage - Weather

  • Are there any other Hazards/Risks

  • Other Hazards
  • Additional Hazards/Risks

  • Additional controls and implementation

  • Photos

7. HRCW on or near pressurized gas distribution mains or piping

7. HRCW on or near pressurized gas distribution mains or piping

  • Working near pressurized gas mains

  • Select Gas asset type

Hazards/Risks

  • Movement of powered mobile plant

  • Refer Section 2 HRCW at workplaces where there is any movement of powered mobile plant.

  • - U.G. asset damage - Striking U.G. assets - Death/injury - Fire - Interruption to Supply

  • VERIFICATION - Asset Owner

  • VERIFICATION - Asset owner on site

  • VERIFICATION - Name

  • VERIFICATION - Emergency Call number

  • Emergency Call 000 and Mobiles Call 112

  • Why is the asset owner not on site

  • VERIFICATION - Allowable Excavation method required to locate the asset

  • VERIFICATION - Gas assets located

  • Minimum clearance

  • VERIFICATION - Clearance in millimetres

  • VERIFICATION - Excavation Method required

  • Refer Section 6 HCRW involving trench or shaft if the excavated depth is more than 1.5 metres

  • Refer to gas provider as listed on MOCS, type and specific excavation requirements

  • Gas Leaks

  • In the event of a gas leak Site Controls required to be implemented

  • Are there any other Hazards/Risks

  • Other Hazards
  • Additional Hazards/Risks

  • Additional controls and implementation

  • Photos

8. Additional HRCW Activities

Additional HRCW Activities

  • A SWMS must be prepared if proposed works involve any additional HRCW activities not listed above and that work poses a risk to the health and safety of any person. Where additional HRCW activities are required, work must cease and SWMS is to be generated.

  • Select all HRCW that applies

  • Specify Other

  • Tasks involved
  • What are the tasks involved? List the work tasks in logical order.

  • What are the hazards / risks? What aspects of the work could harm workers or the public?

  • What are the control measures? Describe what will be done to make the activity as safe as possible.

9. Job Status Review

    Job Status Review
  • When a job stops and re-starts the work party must perform a safety review to identify any further hazards or risks which change as a result answering “YES” to questions below.

    Where additional hazards or risks are identified they must be recorded on the job site SWMS and communicated to all personnel onsite.

  • Has the work scope changed since the initial review?

  • What has changed?

  • What can go wrong?

  • What do we need to do?

  • Are we satisfied with the controls implemented?

  • Why not?

  • Has the environmental conditions changed?

  • What has changed?

  • What can go wrong?

  • What do we need to do?

  • Are we satisfied with the controls implemented?

  • Why not?

  • Has anyone identified any further hazards / risks?

  • List the hazards/risks

  • What can go wrong?

  • What do we need to do?

  • Are we satisfied with the controls implemented?

  • Why not?

Safety Observer

    Safety Observer
  • Name and Signature

  • What is your duty as Safety Observer?

  • List your Safety Observer duties

Sign Off

Sign Off

  • We the undersigned have participated in a worksite discussion using this SWMS and have reviewed the job identified hazards and agree to implement the control measures. All undersigned agree they are fit for work, have the appropriate training and equipment to perform their duties.

    Each crew member and contractor to print name and initial:

  • Work Party Leader

  • Staff Sign
  • Name and Signature

  • Apprentice/Mentor
  • Apprentice

  • Mentor

  • Traffic control
  • Name and Signature

  • Visitor
  • Name and Signature

  • SubContractors
  • Company, Name and Signature

Job Completed Time

  • Job Completed Time

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.