Title Page

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Personnel

Erection & Dismantling

  • Only trained, competent persons involved

  • *Daily Assessment: Need for & feasibility of fall protection. ( During the complete time frame of scaffold erection and/or dismantling, this daily assessment must be made and this checklist signed and dated)

  • Hard hat always worn<br>

  • Other PPE as appropriate; steel toed boots, gloves, eye protection

  • Supported scaffold poles, legs, posts, frames, and uprights resting on base plates and mud sills or other adequate firm foundation

  • Add media

  • Frames, legs, braces: plumb, level and secure

  • Add media

  • Locking Pins: in place and secure

  • Created planks used or planks extend at least 6" and not more then 12" over support.

  • Add media

  • Planks over 10' do not extend more then 18" over support

  • No more then 1" space between platform units as well as uprights

  • Add media

  • Supported scaffold with height to base width greater than 4:1 restrained by guying, tying, bracing, or equivalent means.

  • Add media

  • Safe distance from power lines: <br><br>Insulated Lines:<br>1. Less then 300 Volts: 3 feet<br>2. 300 volts to 50kv: 10 feet<br>3. More then 50kv: 10 feet plus .4" for each 1 kv over 50 kv<br><br>Uninsulated lines:<br>1. Less then 50kv: 10 feet<br>2. More then 50kv: 10 feet plus .4" for each 1kv over 50kv

  • Add media

  • Above 10'; installation of guard rails, mid rails, toe boards

  • Add media

  • Above 2'; access if provided by stairs, ladder, ramp,...

  • Add media

  • Components inspected: defective items removed from site

  • Add media

  • If appropriate, warning signs, barricade tape in place. This would be need if work is commencing on 2 or more scaffolds high.

  • Add media

  • Temporary wiring clear of employee & vehicular traffic

  • Add media

  • Guard rail systems [ on all *open sides and ends] installed before scaffold released for employee use<br>* An open side is greater then 14" from the face of the work except:<br>1. For plastering and lathing, it is greater then 18" from the face of the work<br>2. For outrigger scaffolding, it is 3" from face of work

  • Add media

Scaffold Use

  • Daily Inspection by competent persons. Is this recorded?

  • Only trained employees on scaffolding

  • Hard hats always worn

  • Employees not standing on guardrail a or mid rails or cross rails

  • Employees not standing on boxes or step ladders on scaffold to gain height

  • Add media

  • Potential falling objects, to large to be contained by toe-boards, mess, etc.. Will be placed away from edge.

  • Scaffolds will not be loaded above there capacity. Under no circumstances will platforms deflect more then 1/60 the span when loaded

  • Add media

  • Scaffold planks are in good condition.

  • Add media

Other

  • NAVFAC jobs have correct red or green scaffold tag indication

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.