Information
Document No.
Audit Title
Client / Site
Conducted on
Prepared by
Location
Personnel
Project Safety Plan
1. Has a site specific project safety plan been developed for the project?
Add media
2. Is the plan the current revision
Add media
3. Is the plan approved by the project manager
Add media
4. Is there a document transmittal register that demonstrates the safety plan / project risk register has been communicated to the subcontractors during the contract letting process
Add media
Policies
5. Has the plan been updated to take account of changes in resources, risk or design changes in the project?
Add media
6. Is the current WHS policy statement displayed on the notice board?
Add media
7. Is the current WHS policy statement communicated to site personnel including subcontractors through the induction process?
Add media
8. Is the current rehabilitation policy displayed on the notice board?
Add media
9. Is the return to work coordinator name and number displayed on the emergency contact poster?
Add media
10. Are the details of workers compensation insurer displayed on the notice board?
Add media
11. Is the WHS consultation policy displayed on the notice board?
Add media
Site Registration and Induction
12. Is the sign on sheet in place and in use. (No. Of personnel and subcontractors on site)
Add media
13. Is the site induction register up to date?
Add media
14. How many persons have been inducted?
Add media
Contractual requirement for WHS
15. Are specific contractual/client requirements being communicated to subcontractors?
Add media
Roles and Responsibilities
16. Does the project safe plan contain correct organisational chart and reference current positions?
Add media
17. Have all project responsibilities been allocated and are they current?
Add media
18. Have roles and responsibilities been communicated to all project staff and have they been signed off?
Add media
19. Has a person been nominated specifically for the role of WHS management representative?
Add media
20. Dos the project safety plan include a copy of the site organisation chart which reflects the current resources on the project and their reporting lines for WHS?
Add media
Training
21. Has the project manager identified training needs for project personnel?
Add media
22. Has any training been provided since commencement of project or since last internal audit?
Add media
23. Have details of training been forwarded to the WHS manager?
Add media
24. Has on the job training been recorded and filed?
Add media
25. Are current workers on site inducted and the induction records completed?
Add media
26. Is a copy of each workers WHS induction card, licences and certificates of competency attached behind their induction record?
Add media
Consultation
27. Have arrangements for consultation been agreed? Is there a consultation tool box talk or similar to demonstrate a consultative process?
Add media
28. Is the site safety committee or health and safety representative name/s displayed on the notice board?
Add media
29. Is there adequate representation of workers?
Add media
30. Is the site notice board established? Does it display all items listed in the project safety plan?
Add media
31. Are tool box meetings taking place as required and are records available?
Add media
32. Is there evidence of the project manager attending a TBT or safety walk at least once a month?
Add media
33. Is there evidence of a senior manager participating in safety related information? If so, list the most recent date.
Select date
Add media
34. Are actions arising from site safety walks and tool box meetings signed off as and when they we complete?
Add media
35. Are subcontractors tool box meetings taking place on a fortnightly basis and records available (may be substituted by attending a TBT if the subcontractor is low in numbers)
Add media
36. Is a copy of the toolbox meeting minutes available to all workers?
Add media
37. Is a copy of the current project risk register available to all workers?
Add media
Risk Management
38. Has the project risk register been updated to include all current trades on site including the finding of the safety in design risk assessment?
Add media
Safe Work Method Statements
39. Are SWMS available for all current work being performed on the project?
Add media
40. Do all subcontractors on site have an accepted SWMS (verified by principal contractor)?
Add media
41. Have the workers on site been inducted into and signed their relevant SWMS?
Add media
42. Have SWMS been monitored by use of weekly spot audits
Add media
First Aid and Emergency Planning
43. Is the site maintaining a first aid register of injury record?
Add media
44. Are the site first aid officers names displayed?
Add media
45. Are the site first aides competent and adequately trained? Objective evidence required.
Add media
46. Is the first aid kit stocked in accordance with the first aid code of practice? Is there a first aid room?
Add media
47. Is the correct number of first aid kits available for use and located in accordance with the code of practice?
Add media
48. Have first aid facilities been marked with the appropriate safety signs?
Add media
49. Is the emergency warning system established, tested and known to site personnel?
Add media
50. Is the site covered by the necessary emergency evacuation plans and are they displayed?
Add media
51. Is there an emergency evacuation plan on site providing locations of:<br>- Muster point<br>- Fire Extinguishers<br>- Site amenities <br>- Spill kit locations<br>- Chemical storage location<br>- First aid kit locations
Add media
52. Has an emergency controller been appointed and do they understand what to do in an emergency?
Add media
53. Is there a list of emergency controllers/first aides posted on site?
Add media
54. Has a practice emergency evacuation drill been conducted and recorded initially and then six monthly?
Add media
Hazardous Substances and Dangerous Goods
55. Is the site maintaining a hazardous substances register?
Add media
56. Does the register cover all hazardous substances on site?
Add media
57. Has a risk assessment been performed for all hazardous substances used on the project?
Add media
58. Are hazardous substances and dangerous goods being stored in compliance with satisfactory requirements and/or appropriate standards I.E AS1940
Add media
59. Is there evidence to demonstrate that personnel have been consulted and trained in the handling requirements, PPE to be worn or other control measures to be observed when using hazardous substances and dangerous goods?
Add media
60. Are MSDSs available for all products in use on site and are issue date less than five years old?
Add media
61. Is the hazardous substance register and MSDSs close to first aid facilities?
Add media
62. Are the hazardous substances in labelled containers/packages?
Add media
Inspection of Site
63. Are safety walks and spot audits undertaken at least fortnightly?
Add media
64. Are safety walks being performed by competent personnel and including subcontractors?
Add media
65. Are findings recorded on the safety walk form?
Add media
66. Are significant findings linked to the issue of non conformance reports?
Add media
67. Are identified (observations NCRs) issues closed out?
Add media
Inspection - Plant and Equipment
68. Are plant certification records available?
Add media
69. Are planet and risk assessment records available for all high risk (mobile) items of plant?
Add media
70. Is the plant and equipment register maintained?
Add media
71. Are records of defects noted during plant startup checks?
Add media
72. Are maintenance and service records available for all plant on site?
Add media
73. Are electrical test and tag records available for all electrical equipment on site including subcontractors?
Add media
74. Are non conformance reports raised for significant safety breaches or non conformances?
Add media
75. Are all identified issues signed off and completed within the required timeframe?
Add media
Non Conformance and Non Conformance Reports
76. Where the non conformance reports relate to a dangerous occurrence, has the regulator been notified in the prescribed manner?
Add media
77. Are incident/dangerous occurrence investigation reports completed as required and corrective action implemented based on risk?
Add media
78. Are early notification of workplace injury forms completed and sent to the RTW coordinator?
Add media
79. Have issues identified in any regulator notices issued been dealt with and finalised?
Add media
80. Have issues identified by client audits been dealt with and finalised?
Add media
WHS Audits
81. Has an internal audit schedule been established for the project?
Add media
82. Have audits been performed in accordance with the schedule?
Add media
83. Have all non conformances raised by the audit been closed out and signed off?
Add media
Legislation/Records Management
84. Are project records being maintained as per the requirements of the IMS?
Add media
85. Is legislation, codes of practice and Australian standards readily available to all site staff?
The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions.
The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice.
You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction.
You should independently determine whether the template is suitable for your circumstances.