Foundation Checklist

Grading and Erosion Control

  • Post lot sign and permit board. Paint property lines on curb

  • Is the building pad level?

  • Are the swales cut in and is the drainage in compliance with the HLP?

  • Is the C.O. Pad and garage on the high side of the lot?

  • Is the silt fence and C.O. Installed per the county and EPD requirements?

  • Is a compaction letter required? If the lot elevation has been changed in excess of 2' a new compaction letter is required.

  • Are there any obstructions with regard to driveway?

Foundation Box

  • Check the box dimensions and square

  • Confirm the garage side

  • Mark the form boards for any brick ledge

  • Confirm the patio locations and size. The front patio needs to be offset 4" to accommodate the columns

  • Have the forms checked by the surveying company to ensure the location of the home is in accordance with the HLP

  • Is the box within the setback and or property lines

Slab Plumbing

  • Check for 1/8" per foot fall on all drain lines. Make sure drain lines are bedded in ground and partial covered with dirt.

  • Check for leaks-look for wet dirt

  • Ensure PVC sleeve is installed at main drain as it exits slab and at footings

  • Check that pipes are secured to metal stakes and are located in the proper locations

  • Make sure there are no splices in the supply lines

  • Make sure the island conduit is installed in the correct location if it is required

  • Confirm the locations of all pipes, i.e. kitchen, bath, and water heater

  • Check for sleeves at Thickened Slab areas

Slab Prep

  • Footing dug square and free of debris and loose dirt. Rebar must be centered in footing and placed on chairs

  • Grade beams in rebar installed per plan/details

  • Turn up rebar ground in outside garage wall near electrical meter base location

  • Vapor barrier installed and wall straps/bolts on-site for insulation during concrete pour

  • Ensure form boards are straight and properly braced

  • Double check slab dimensions, square, and patio dimensions and locations

  • Confirm water and power meters are set

  • Check for positive slope 3" in 20' on garage

  • Visual Failures

  • Notes

  • SDH Builder/Employee

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.