List the documents that have been provided to review as part of this process
-
Has the Project Scope been included?
Workplace Control
-
Have contact details for Client, Contractor Site Representatives and any other relevant personnel been included?
Notifiable Works
-
Does the scope of works require Notification of Works to Worksafe and if so has a notification been submitted?
Safe Work Practice and Risk Assessment
-
Has a Risk Register been included, identifying site specific hazards and risk?
-
Have suitable controls been identified and included for relevant risks within the Risk Register?
-
Are any high risk, critical risk or notifiable works required and if so, have suitable Risk Assessments been provided?
-
Are any permit to work procedures in place / required?
-
Is an Emergency Response Plan required and if so, has this been provided?
-
Will Hazardous Substances be used on the worksite? If so, has a hazardous substance register been provided?
-
Have Safety Data Sheets been supplied / recorded relevant to any Hazardous Substances that will be used?
-
Are minimum PPE requirements in place?
Induction, Training and Competency
-
Is there an induction process in place for employees, subcontractors and relevant visitors?
-
Do workers comply with any client minimum standards such as Construct Safe, Site Safe Passport?
-
Are workers suitably trained relevant to the tasking required and use of plant/equipment?
-
Has a Training/Competency Register been provided?
-
Will untrained workers be fully supervised whilst on site?
Environmental
-
Will noise, dust, fumes, smoke be generated that could affect other workers or members of the public? If yes, have suitable controls been identified to manage associated risks?
Emergency
-
Have Emergency situations been assessed and planned for?
-
Will Emergency Equipment be available on site?
-
Are Emergency Procedures in place that reference Medical Centres, Hospital, Emergency Equipment etc?
-
Are Emergencies practised / tested and if so at what frequencies?
Subcontractors
-
Will the contractor be engaging subcontractors as part of project work requirements? If so, have additional SSSP details for each contractor been provided and reviewed?
Consultation, Co-ordination and Co-operation
-
Prestarts - will these be conducted and if so at what frequency?
-
Toolbox Talks - will these be conducted and if so at what frequency?
-
Safety Meetings / Other - will these be conducted and if so at what frequency?
-
Will evidence for the above be recorded formally via meeting minutes?
Monitoring and Review
-
Will safety inspections be conducted of the work site / task area? If so, how often will these be completed and will evidence be available if requested?
-
Will Plant and Equipment be regularly maintained and inspected before use? If so, how often will these be conducted and will evidence be available if requested?
Incident Reporting
-
Is there a process for the reporting and recording of incidents and near misses?
-
is there a process for undertaking investigations of incidents and injuries?
-
Is there a process for reporting serious harm to Worksafe?
-
Is there a process for corrective and preventative actions?
Other
-
Is there a procedure for waste management?
-
Is there a procedure for security?
-
Is there any requirement for Traffic Management
-
Is Asbestos a risk and if so, have suitable plans been established for demolition/removal?