Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
SMS Form - Site set up check list (Draft)
-
-
HSE Checklist - Principal Contractor Site Set up Checklist
Documents/Equipment
-
In Files
-
Display
-
Install
-
Company Health & Safety Policy
-
Public Liability Policy
-
Employers Liability Policy
-
Form F10
-
‘Health and Safety at Work’ Law Poster
-
Asbestos register
-
Construction Phase Plan
-
Project Directory/Contact list and numbers
-
Site/Clients Rules (Where applicable)
-
Current & Relevant Health and Safety Memos and Bulletins
-
Induction Procedures to include list below:
-
Site Rules/Procedures
-
Accident Reporting procedures
-
First Aid procedures
-
Risk/COSHH Assessments & Method Statements
-
Signing In/Out procedures
-
Equipment Inspections
-
Induction Record Form
-
OHH Construction Site Office sign
-
Safety Signage:
-
Safety Hats
-
Safety Footwear
-
Ear Protection
-
Evacuations procedures
-
Eye Protection
-
Face Protection
-
Hi-Vis
-
Hand Protection
-
Emergency Exit - various
-
‘Fire Point’
-
Fire Appliances – Water, Foam, Co2 etc
-
First Aid Room
-
‘Assembly Point’
-
‘No Smoking’
-
Fire Appliance/s in Site Office and around Site:
-
Water, Foam, CO2 etc
-
Copy of Site Fire Plan/Evacuation Procedures:
-
(Up-dated during project)
-
First Aid Kit
-
List of First Aiders and Appointed Persons
-
Fire Assessment carried out for building/site
-
Documents/Equipment
-
In Files
-
Display
-
Install
-
Toolbox Talks
-
Plant/Equipment Inspections Registers plus use of Scaftag system for mobile working platforms and steps
-
Permit systems in place?
-
Permits to Work
-
Hot Works Permit
-
Access Permits
-
Works at Height
-
All office electrical equipment to have current PA Test certificate/stickers (Where Applicable)
-
All Sub-Contractors electrical equipment to have current PA Test certificates/stickers
-
Site Documentation: Must be available in hard copy
-
Accident Book
-
Accident Investigation Form
-
Site Safety Report Form
-
Manual Handling Assessment Form
-
PPE Checklist
-
Site Safety Awareness Briefing Notes
-
Site Health & Safety Induction Training Records
-
Risk Assessments
-
Method Statements
-
COSHH Assessments
-
Site Welfare (See Data Sheet)
-
Toilets (Check HSE Guidance Notes on quantity)
-
(Male & Female)
-
Welfare:
-
Hot & Cold Water; Fridge:
-
Microwave; Kettle/Water Boiler;
-
Tables & Chairs;
-
Rubbish Bin etc
-
Drying Room c/w Heater
-
Hand Cleaner (Dispenser)
-
Hand Cream (Dispenser)
-
Soap
-
Paper Towels
-
Rubbish/Dust Bin
-
Security Fencing (Where applicable)
-
Security Fencing/Perimeter Signage (Where applicable)
-
Document/Equipment
-
In Files
-
Display
-
Install
Training Records:
-
Abrasive Wheels
-
Mobile Towers (PASMA)
-
MEWP’s
-
Confined Spaces
-
First Aid/Appointed Person
-
Manufacturer’s/Suppliers information on safe use of plant & equipment on site
Inspection Records:
-
Mobile Towers
-
Stepadders
-
Site Safety