Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Authority for administration of "Quality Management System"
-
Full authority has been delegated to defined position
-
The Designated Authorised Person retains an up to date copy of "Boiler Quality Manual"
-
At all times the requirements of the Boiler Operating and Maintenance system takes precedence over any other non-safety priorities.
-
Person in control of boiler management is adequately trained and understands the "Code of Practice for the Safe Operation, Maintenance and Servicing of all Boilers having a Power Output of Less than 20MW"
Responsibility and training - It is essential that at all times, Management are satisfied the boiler installation is under the supervision of a trained operator
-
The General Manager is satisfied that all operators have the appropriate experience and training
-
The Plant Manager is satisfied the boiler installation is under the supervision of a trained operator
-
There is a roster in place of "Responsible Person" to take corrective action and reset the boiler if required
-
Staff are aware of the "Responsible Person" roster and procedures to follow if this person is not immediately availabe
-
Training records are maintained designating - Employee name, Trainer name, Subject, Date of training and the venue
-
Training records are signed by the Training Officer
-
An up to date version of "Boiler Quality Manual" is available to operators at all times
Routine records
-
"Daily Log Sheet" records are maintained
-
The Engineering Manager conducts regular checks to ensure this being maintained
-
Weekly checks are recorded in the "Weekly Log Sheet"
-
Monthly checks are recorded in the bottom portion of the "Daily Log Sheet"
-
"Quarterly Maintenance Schedule is completed by the service organisation
-
"Annual Inspection" reports from Inspection Agency are submitted for corrective action and filing
-
Annual "Boiler Quality Management System" audit reports are submitted for corrective action and filing
-
All "Non-Routine" records are filed for a period of 5 years
Quality Records
-
A binder is in use to store relevant Quality Records (refer section 1.4.6 for a full list)
-
A "Vessel Dossier" is maintained with copies of Hydro-Static tests
-
A "Water Treatment Manual" is available
-
A "Log Book" is maintained detailing (Daily, Weekly, Monthly) checks
-
A Maintenance Manual is available to Service Personnel
Non Conformance Reports
-
"Non Conformance Reports" are raised any time the plant falls outside of routine operating conditions - e.g. A lock out, or unsatisfactory internal inspection, or unsatisfactory boiler water analysis results, etc.
-
"Non-Conformance Reports" details follows the set format as set out in the "Boiler Quality Manual" (section 2.7.1)
-
"Non-Conformance Reports" are raised by those indicated in "Boiler Quality Manual" (section 2.7)
Repairs and Modifications
-
Repairs affecting the safety of the plant are carried out by the "manufacturer, their designated agent or by an organisation approved by the Inspecting Authority"
-
Details of the repair, and subsequent inspection records are appended to the vessel dossier.
-
Details of repair or modification are registered in the "Modification and Repair Register"
-
Any modifications have been approved by the Inspection Authority and the Manufacturer or their designated agent
Document Control
-
Documents are Approved, Reviewed, controlled and Issued by Authorised Personnel
-
The "Boiler Quality Manual" is revised by the Authorised Person or his Nominees
-
All revisions are approved by the Plant Manager
-
A "Document Register" is maintained and current
-
Quality documents are issued on a controlled basis via "Document Distribution Registers"
-
Only current versions of documents are available for use
Purchases
-
All purchase orders contain a full description of the goods and services ordered
-
All received goods and services are verified to comply with order conditions prior to release for use
-
Purchased goods are stored in an appropriate area
-
Any "Sub Standard" services are recorded on a "Non Conformance Record"
Calibrations
-
The "Main Boiler Pressure Gauge" is periodically calibrated in compliance with the appropriate Code of Practice
-
Calibration of the Main Boiler Pressure Guage is conducted by an IANZ registered laboratory
-
Other devices or instruments are calibrated as required or if damage is apparent
-
A Calibration Record is maintained for each device or instrument
-
Each device or instrument is marked with a label indicating calibration expiry date