Title Page
-
Capital Deliver Package of Work
-
Conducted on
-
Prepared by
-
Who?
Management
-
Senior Manager Responsible for Railway Safe System of Work Planning (RSSP Manager) Appointed? (RIPS & Deputy RIPS)
-
F2001A process completed to nominate and appoint SSOW Responsible Manager – photo/copy of appointment
-
Give Further Details
-
Name of SSOW Responsible Manager
-
Appointed SSOW Responsible Manager has requested the track access via the possession planning department using the standard application form & process.
-
Give Further Details
-
For use of Site Wardens in separated SSOWs, has an F2001B form been completed, submitted and processed with authorisation by RSSP Manager/ deputy RSSP Manager(s)
-
Give Further Details
-
If F2001B has been used for Site Warden arrangements, has 7 days notice been provided and has NR Programme Manager been asked for comments/objections/challenges. Evidence of email needed.
-
Give Further Details
-
For use of Open Line access only (no working) to track using lookout/ equipment warning has F2001B process been used and has RSSP Manager acceptance and authorisation been given? Was 28 days notice provided?
-
Give Further Details
-
For open line working activities using lookout operated/ equipment warning systems, has F2001B process been used and has the NR Regional Director provided formal acceptance & approval? Was 28 days notice provided?
-
Give Further Details
-
For Line Blockages - Has Line Blockage authority process been followed by the SSOW RM, and has authorisation been given by RSSP/Deputy RSSP?
-
Give Further Details
-
In DC Areas - Has Live Conductor Rail authority process been followed by the SSOW RM, and has authorisation been given by RSSP/Deputy RSSP?
-
Give Further Details
-
Do access points have clear labelling
-
Give Further Details
-
Where ALO work is underway, has an ALO Responsible Manager, ALO Planner, ALO Site Controller and ALO assurance checker been appointed – and have they been trained by us?
-
Give further details
-
Is the ALO plan in date and accurate for the plant, location and activity?
-
Give Further Details
Planning and Resourcing
-
Name of Possession Planner
-
Does Possession Planner hold a valid SSOW Planner competence – photo & expiry date expiry date
-
Give Further Details
-
Name of SSOW Planner
-
Does SSOW Planner hold a valid SSOW Planner competence – photo & expiry date expiry date
-
Give Further Details
-
For Line blockages, has the hierarchy of line blockage protection been adhered to (i.e. LB only, Token, Signal disconnection, EPR, T-COD, Dets)?
-
Give Further Details
-
Does the SSOW limits cover the work location and access / egress points?
-
Give Further Details
-
Has the SSOW Planner undertaken an independent check of the suitability of the limits?
-
Give Further Details
-
Has the SSOW Pack included annotated diagrams for the limits and access points? (including for CPs and strapmen?)
-
Give Further Details
-
What COSS classifaction level should be used as a minimum?
-
Has the COSS/PC/CP/MC achieved the COSS level of classification required? (gold, silver, bronze etc)
-
Give Further Details
-
Has the COSS/PC/POS/MC/CP/Strapman (at COSS level) been allocated to the job at least 5 days in advance?
-
Give Further Details
-
Has the Site Warden changed inside 48 hours of the start time?
-
Give Further Details
-
Where COSS/PC/CP/Strapman/MC/POS have changed inside 5 days (for levels 1, 2 &3) has the F2001C process been used correctly with suitable ‘exceptional circumstances’ justified?
-
Give Further Details
-
Has the COSS/PC/CP/Strapman/POS worked at the site within the last 6 months and has sufficient local knowledge? (3months for any open line access/open line working)
-
Give Further Details
-
If not sufficient local knowledge, has a site visit been carried out on days (applies to those allocated to day and night shifts)?
-
Give Further Details
-
Was the SSOW Pack verified at least 12 hours prior to the start of the shift (for COSS, SWL1, PC, Machine Controller, POS Rep)
-
Give Further Details
-
Has a challenging conversation been completed between the RM & COSS/MC/PC/CP/POS and has this been recorded? If not, why?
-
Give Further Details
-
Have CPs and strapmen been provided with a SSOW pack for their specific duty?
-
Give Further Details
-
Do Machine Controllers have valid competence certificate, an LLT, Proving unit, dets, flags, Track circuit operating clips, dect comms/duplex communications in place with spare kit?
-
Give Further Details
-
Has an RRV check list been completed for the job – if RRVs are being used?
-
Give Further Details
Completion
-
Please schedule out any Improvement opportunities or areas of concern
-
Signed by individual completing audit/checks