Title Page
-
Inspection date:
-
DA Number:
-
CC / CDC Number:
-
Address of inspection:
-
Inspection Result
- The inspection was satisfactory
- Work/certificate required - no reinspection needed
- Work required - reinspection required within 30 days
- Stop works immediately and contact Council officer
Inspection Details
-
Inspection able to be completed?
-
Complete footings / steel reinforcement and re-book inspection prior to pouring.
-
Provide access to the site and re-book inspection.
-
Full or partial inspection undertaken?
General
-
Is the site adequately fenced or access to site appropriately restricted?
-
Fence off or restrict unauthorised access to the site in accordance with SafeWork NSW and WHS Regulation requirements.
-
Is the site clean?
-
Remove all rubbish and waste from the site.
-
Is the site free of undue hazards?
-
Are sediment and erosion controls satisfactory?
-
Provide sediment and erosion controls on site in accordance with the requirements of the development consent and any stamped approved plans.
-
Are appropriate facilities provided for workers?
-
Does the site have appropriate builder's signage and Principal Certifier signage?
-
Provide Principal Certifier / builder's signage in accordance with the requirements of the development consent and Clause 98A of the Environmental Planning and Assessment Regulation 2000.
-
Validation certificate required for imported fill?
-
Are all applicable development consent conditions being complied with?
Footings / Steel Reinforcement Inspection
-
Is the vapour barrier complete and intact?
-
Are all earthworks / formworks consistent with the stamped approved plans?
-
Is the reinforcement steel size in accordance with the approved details?
-
Is the reinforcement steel adequately lapped?
-
Are all piers / footings free of debris and water?
-
Clear all piers / footings of all debris and/or water prior to pouring.
-
Is the formed slab / building element within peg out area?
-
Is all steel reinforcement adequately tied?
-
Is all steel reinforcement adequately chaired?
Additional requirements
-
Additional Requirements?
Inspection completed by:
-
Signature:
-
BPB accreditation number: