Information
-
Job site address
-
Supplier/Subcontractor
-
Supplier/Subcontractor Work Activity Supervisor
-
How many workers does the Supplier/Subcontractor have on site today?
-
Conducted on
-
Prepared by
-
Location
Audit item to be checked
-
Have all workers been inducted and signed the Site WHS Management Plan?
-
Has the Work Activity Supervisor and each worker signed the Safe Work Method Statement (SWMS) if they are performing a high risk activity?
-
Are all workers carrying their White (or equivalent) Construction Industry Induction Cards?
-
Is a first aid kit available for the workers to use on site?
-
Are Safety Data Sheets available for all Hazardous Materials use on site?
-
Are all electrical tools and leads tested and tagged at three monthly intervals?
-
Is an RCD (safety switch) portable power board being used (domestic power boards are not permitted)?
-
Is any working at heights being performed, and is it being done in a safe manner?
-
Are scaffolds and trestles (above 2m in height) compliant, fully planked with appropriate access?
-
Are heavy duty ladders being used on site and tied off when accessing roofs?
-
Is Personal Protective Equipment (PPE) being work appropriately?
-
Is the operator of plant appropriately licensed and has a plant Prestart checklist been completed?
-
Is the Devine UV Sun Smart Policy being followed on site?
-
Is appropriate supervision being provided by the subcontractor to young workers on the site?
-
Any other safety related items that require corrective action by the subcontractor?
Safe Work Method Statement Review (if no high risk activities are being undertaken by this subcontractor, please mark all questions below as "Not Applicable")
-
Does the SWMS detail the subcontractors company details?
-
Does the SWMS detail the name of the person responsible for developing and approving the SWMS?
-
Does the SWMS detail the name of Devine Homes as the Principal Contractor?
-
Does the SWMS have the job site, lot number or address of where the work is carried out listed on the SWMS?
-
Does the SWMS list the steps that must be taken to safely carry out the high risk works, and the control measure of how risks will be managed?
-
Have all workers performing the high risk task signed into the SWMS?
Safety Non-Conformance Notice
-
Was a Safety Non-Conformance Notice issued? (If yes, please forward a copy to the EHS Manager)
Approval
-
Add signature
-
Site Manager Name
-
Select date