Title Page
-
Jicarilla - 021579 - 0372
-
Conducted on
-
Prepared by
-
Location
Jicarilla BESS Project
-
Instructions : SunGrid supervisor complete this checklist every work day at each project site (Tier 1). They are consolidated weekly to SunGrid leadership (Tier 2) and a summary of compliance and corrective actions to close gaps escalated to the Honeywell project leaders (Tier 3)
Signature Section
-
Monday
-
Tuesday
-
Wednesday
-
Thursday
-
Friday
Task Risk Assessment or JSA
-
Was a JSA completed?
-
Have all job steps been listed
-
Have all hazards been identified?
-
Have all hazards that have been identified been mitigated with control measures?
-
Have all PPE been identified and used
-
Have SIMOPS been identified
-
Have all workers for task signed the JSA
Review of: expectation around Life Saving Commitments
-
Is Stop Work used when unsafe?
-
Say no to drugs an alcohol?
-
Follow Safety Controls?
-
Practice Safe Mechanical lifting?
-
Follow Driving and Traffic Rules?
-
Verify Isolation before work begins?
-
Is Hot Work safely performed?
-
Only enter confined space with authorization
-
Stay away from line of fire hazards
-
Careful when working at height?
Daily / weekly equipment checks
-
Specify the weekday of the review
Weekly facility checks (e.g. fuel tanks, other support equipment on site)
-
Specify the weekday of the check
Weekly job audits of site – completion and findings
-
Weekly job audit completed?
-
Pictures of findings
-
Specify the weekday of the audit
-
Incidents reported / near misses encountered
General Safety
-
First Aid kit onsite
-
Eye wash stations onsite and full
-
Job site orientations completed
-
Spill kits onsite and full
-
Supervisor onsite