Site establishment
-
Builder sign in place & Visible.
-
Silt fence & driveway gravel in place.
Frame Position
-
Check external wall bottom plates do not overhang more than 10mm.
-
Check the external wall bottom plates are not more than 20mm in from the edge of the concrete.
-
Is rebate (brick/AAC/Cladding) correct size & location.
-
Check if lightweight zero lot wall and corner frame internal pins for its position.
-
Check walls are per plan in positioning.
-
Check gaps/dips in slab bottom plates
-
is termite film installed all perimeter.
-
Is 110mm dampcourse stapled to all external bottom plates & wet area walls.
Tiedown/Bracing
-
Tie down fixings to slab at least 50mm from slab edge.
-
Tie down rods/bolts per approved plans & fixed, rods clear of roofing battens and sheeting at top.
-
Cyclone straps to trusses with 6mm mech driven fixing each side
-
Strap lintel to ribbon plate- min 6 nails each side.
-
Provide batten screw connection/creeper bracket to all hip creeper rafters that exceed 1800mm.
-
All wall bracing in position as required on approved plans and properly fixed including tie-down rods, nails not overdriven.
-
Ply bracing nailed off correctly 50mm top/bottom, 150mm sides,300mm internal fixings.
-
Transfer noggings installed connecting bracing walls to trussed roof frame -batten screwed, not nailed.
-
Non load bearing walls connected to trusses with slotted wall brackets where required.
Other
-
Truss layout consistent with the truss plan and fixed at correct centers-rafters/truss strapped to head within 100mm of each truss
-
Are any standard trusses bowed
-
Studs under point loads/girder trusses
-
Roof and truss point loads supported and blocked if required.
-
Check A/C opening space/location.
-
Are steel posts installed. If not will they be ready for lock up?
-
Review beam connections
-
Timber posts cup heads to face the street, recessed washer/nut.
-
is the timber frame mould affected?
-
Check waste pipe locations are per plan.
-
Check floor joist layout as per plan.
-
Particleboard flooring glued/screwed per layout pattern.
-
All boots nailed/screwed correctly.
-
Balcony beams & Joists installed & ends sealed
-
Are fall guards in place-void/openings