Title Page

  • Site conducted

  • Date of Pre Plaster Assessment

  • Assessment Completed by

  • Site Supervisor

  • Job Address

Internal

  • ● Has the frame inspection been approved?

  • ● Are all door openings framed to the correct size?

  • ● Are all cavity sliders installed & fit in openings correctly?

  • ● Are all specialty door pockets & trackes installed?

  • Location

  • ● Have all noggins been installed for any specialty door tracks etc?

  • ● Have all wall junctions been plumbed and nail off?

  • ● Is bracing nailed back flush and on the hollow side of studs?

  • ● Have all packers been nailed off and feathered at top and bottom?

  • ● Have Internal wall brackets been installed correctly to wall top plates?

  • ● Have all studs been straightened?

  • ● Are all bulk heads and drop ceilings level and straight?

  • ● Have noggins been installed for towel rails, toilet roll holders etc?

  • ● Have noggins been installed for Garage door mounts?

  • ● Have noggins been installed for stair handrail/wall junctions?

  • ● Have change of direction noggins required for plaster battening?

  • ● Is bath hob installed where required?

  • ● Has villa board been installed to bath hob with angles?

  • ● Has tile underlay been installed with plaster angle around perimeter?

  • ● Are niches correctly framed with niche box installed?

  • ● Are all windows plumb and square?

  • ● Has front door and other external doors been installed with hardware?

  • ● Is plumbing stacks and duct pipe framed in where required?

  • ● Does the stair walls line up?

  • ● Has the heating and cooling rough-in been completed?

  • ● Has the plumbing rough-in been completed?

  • ● Has the electrical rough-in been completed?

External

  • ● Have all walls been straightened? Foam render wall N/A

  • ● Has breather wrap been installed to all external walls?

  • ● Have all aluminium window flashings been installed?

  • ● Has wrap been taped on the outside of the window flashing?

  • ● Have all windows been taped to wrap using thermakraft tape?

  • ● Have eave sheets been installed level with joining strap?

  • ● Has the external cladding been made 100% water tight?

  • ● Is Cladding installed in accordance with install guides?

  • ● Is there adequate drip edges for first floor cladding?

  • ● Does all lower floor cladding cover bearers where applicable

  • ● Does breather wrap extend below FFL?

  • ● Has ember mesh been installed for the sub-floor if required?

  • ● Have all external flashings been installed?

General

  • ● Has the site been left clean and clear for the plasteres?

  • ● Is the site bin empty ready for plaster offcuts?

  • ● Have the internals been swept out?

  • ● Have all leftover materials been stacked neatly and out of the way?

  • ● Is the gate locked after every day?

Completion

  • Additional Comments

  • Supervisor Sign Off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.