Information
-
Station
-
General Manager
-
Maintenance Vendor
-
Audit Start Date and Time
-
Auditor
GSE Maintenance
Site Office
-
Verify daily checks are completed and logged
-
Equipment issues being reported
-
Equipment logs maintained
-
Equipment Out Of Service log/board up to date
-
ATA Documentation maintained
Shop/Part Room
-
Shop cleaned and organized
-
Shop equipment operating and properly maintained
-
Part organized and properly stowed
-
Inventory matches Maximo
Maintenance Vehicle Inspection
-
General Checklist used to inspect GSE
Equipment
-
Equipment type
- Car
- Truck
- Golf Cart
- Belt Loader
- GPU
- Air Start
- Bag Tractor
- AC Unit
- Bag Cart
- Access Ramp
- Lav Unit
- PushBack Tractor
- Valet Cart
- Tow Bar
- Loader
-
Equipment #
Paperwork
-
Unit PMs and ATA paperwork are up to date and current?
-
Verify that any recent repairs had been properly completed
General Inspection
-
General equipment body condition
-
Equipment has proper approved markings (decals, Logos, etc..)
-
Interior and exterior cleaned (no FOD)
-
Tires in serviceable condition
-
No leaks visible
-
Operator panels and controls are clearly labeled and operating properly (if applicable)
-
Parking brakes functional
-
If applicable ensure all lights working properly
-
Steering function operate smoothly
-
Is this a motorized unit?
-
Driving operations work smoothly
-
All fluid levels at correct amount
-
Battery Condition
-
Horn operational
-
Back-up horn operational (if applicable)
-
Windshield wipers functioning and in good condition
-
Fuel and quantity gauges working properly
-
Fuel filler cap is clearly marked and closed
-
Gear shift selector is clearly marked (Indictor works correctly)
Special Features
-
Equipment service features operating properly (pumps/belt operations/generators)
-
All safety interlocks operate properly
-
Hoses are free of damages and properly stowed (if applicable)
-
Emergencies Shut-Off Functioning (if applicable)
-
Fire extinguishers are tagged and current (If applicable)
-
Is this unit a piece of fueling equipment?
-
Meter Sealed
-
Accumulators Pressure set properly
-
Primary and Secondary regulators set to 40/50 PSI
-
Overfill protection operating properly
-
Is this Unit a Deicer?
-
DeIcer Units- Pumps operate
-
DeIcers Units- Heaters operational
-
DeIcer Units- Bucket condition and operations satisfactory
-
DeIcer Units- Communication operational
Closing
Findings
-
Gather all critical findings and add them here. Once completed this information is share to the responsible party members for corrections.
-
30 day response time for all findings considered Minor or below
-
10 day response time for all findings considered Major or higher
-
Findings
Issues
-
Issue
-
Severity
-
Comments
Audit Completion
-
Completion Date and Time
-
Auditor