Site Information
-
NPDES Tracking Number
-
Project Name
-
Project Location
-
Inspectors Name
-
Inspection Date
-
Type of Inspection
- Regular Weekly
- Pre Storm Event
- During Storm Event
- Post Storm Event
-
Is the SWPPP binder on-site with records available?
-
Is the SWPPP drawings on-site and current?
Inspection
Weather Information
-
Upload NOAA screenshot of current weather conditions
-
Has there been a storm event since the last inspection?
-
Have any discharges occurred since the last inspection?
-
Are there any discharges at the time of this inspection?
Site Specific Best Management Practices (BMPs)
-
Are construction entrances/exits stabilized?
-
Is silt fence stabilized along roadways?
-
Is silt fence stabilized along woodlands and grassy fields?
-
Is silt fence stabilized along any creeks and drainage ditches?
-
Materials Staging and Storage Areas
-
Dumpsters and Trash Cans
-
Sanitary Facilities
-
Vegetated Swale(s)
-
Sediment Trap(s)
-
Soil Stockpile(s)
-
Topsoil Stockpile(s)
-
Mulch Stockpile(s)
-
Storm Drain Inlets
-
Concrete Washout Area(s)
-
Paint Washout Area(s)
Overall Site Issues
-
Are all slopes and disturbed areas around the site that are not actively being worked on properly stabilized?
-
Are all natural resource areas (e.g., streams, wetlands, mature trees, etc.) protected with barriers or similar BMPs?
-
Are perimeter controls and sediment barriers adequately installed (keyed into substrate) and maintained?
-
Are discharge points and receiving waters free of any sediment deposits?
-
Are storm drain inlets properly protected?
-
Is the construction entrance/exit preventing sediment from being tracked offsite and into the street?
-
Is trash/litter from work areas collected and placed in trash cans or dumpsters?
-
Are washout facilities (e.g., paint, stucco, concrete, etc.) available, clearly marked, and maintained?
-
Are vehicle and equipment fueling, cleaning, and maintenance areas free of spills, leaks, or any other deleterious material?
-
Are materials that are potential stormwater contaminants stored inside, under cover, or protected?
-
Are non-stormwater discharges (e.g., wash water, dewatering, etc.) properly controlled and protected?
-
Were incidents of non compliance found during this inspection?
-
Were all responsible parties notified of their deficiencies during this inspection?
Site Conditions
-
Are there any areas around the site where water ponds?
-
Are all ponding areas being pumped out and cleared?
-
Are dust control measures being utilized as needed?
-
Are site roadways being swept and cleaned as needed?
-
Are public roadways being swept and cleaned as needed?
-
Are there any washout in the grade around the perimeter of the site?
-
Are all filters/liners free from rips or tears?
-
Are all filters/liners clean?
-
Are all BMPs in correct locations and installed per details?
-
Completion
-
By signing this report, I hereby certify that I walked the jobsite and verified all conditions to the best of my ability. This report does not serve as the official record by the civil contractor but as a copy for the General Contractor to verify we are doing our due diligence in making sure we maintain our jobsite as well as possible.
-
Inspector Name
-
Date and Time
-
Signature