Title Page
-
Conducted on
-
Reporter's Name & Company Represented:
-
Location
INSPECTION DETAILS
-
Reporter Job Title:
-
Company Inspected:
-
Works Team Name / Reference
-
Contractor Works Manager / Supervisor:
-
Team Leader's Name:
-
no. of Operatives on Site:
-
Works Vehicle's Registration no.
-
LCRA Borough PERMIT no.
-
Job Pack / section Reference:
NRSWA RESTRICTIONS
-
Has Inspection Lead had to order the suspension of works?
Quality and Safety
1.0 Site Safety
-
Is all required PPE available and being worn for individual tasks?
-
Is a First Aid Kit available, in a satisfactory and replenished condition?
-
Do the team have access to adequate welfare facilities?
-
Is there a copy of the contractor Incident Management Plan?
-
Are gas cylinders secured & stored correctly - IF APPLICABLE?
-
Are all hand tools in good condition and meet the requirements of standard issue?
-
Are all power tools in good condition and being used safely?
-
Are vibrating tools maintained in good working order?
-
Is all Vibrating Equipment assessed and tagged?
-
Are appropriate Cable Locators available, calibrated and in use?
-
Is Gas Detection Equipment on site appropriate, in working order and correctly used, - IF APPLIABLE?
-
Are the correct type of chamber and joint box/cabinet keys available?
2.0 Vehicles
-
Do vehicles have working beacons and approriate chevron markings?
-
Are vehicles tidy and clean?
-
Are vehicles parked safely & securely without causing obstruction?
3.0 Work Pack & Site Documentation
-
Are suitable utility Drawings in pack & Are safe dig drawings on site within 30 day expiry period?
-
Is a legible copy of the work pack/order on site and understood?
-
Are Site Specific Risk assessments in place?
-
Have works been undertaken as planned?
5.0 NRSWA
-
Has the appropriate opening notice/permit to work been raised and is available to view on site?
-
Are there persons on site with the correct NRSWA certification?
-
Is the Signing & Guarding Layout in accordance with the ACOP?
-
Is the site clearly signed and directions understandable by motorists or pedestrians
-
Are all works taking place within a safely barriered area?
-
Are the correct Works information boards provided and in use?
-
Do information boards display appropriate notification and contact numbers?
-
Are signs, cones, barriers etc, clean and in good condition?
-
Are kerb ramps and pedestrian ramps in use where necessary?
-
CSCS accreditation card available, If Applicable?
Civils In Progress
6.0 Civils Excavation, Duct Laying & Reinstatement
-
Is the size and method of excavation suitable for the works?
-
Is the ducting the correct size, type, and colour and free from damage?
-
Is the apparatus orientation & depth of cover appropriate?
-
Duct repairs have appropriate duct repair kits & split duct been used?
-
Are prepared edges sawn vertical, square and sealed?
-
Have the correct backfill and reinstatement materials been used?
-
Are reinstatements free from material crowning and match existing profile?
-
Are reinstatements free of surface depressions and match existing profile?
-
Is the reinstatement and surrounding area free from Road / Cut Off Saw overcuts?
-
Is all permanent or temporary reinstatement acceptable to SROH?
-
Are all kerbs, studs and markings replaced/reinstated to original condition?
-
On Completion of works has the site been left in a safe and satisfactory condition?
-
Has the appropriate closing Notice been submitted (i.e. permanent or temporary reinstatement)?
7.0 CIVILS CHAMBERS
-
Are chambers the correct size & built as planned?
-
Are chambers built to the correct specification?
-
Are duct entry numbers correct and suitably located?
-
Are all frames & covers the correct type and securely fixed?
-
Are all covers to British Standards, kite marked and suitable for intended use?
-
On Completion of works have the chambers been left in a satisfactory condition and clear of debris?
8.0 CIVILS CABINETS
-
Is cabinet used the correct type and specification?
-
Is the cabinet shell correctly painted, undamaged and water tight?
-
Is the cabinet securely fixed to the base?
-
Have the correct number of duct entries been provided and in the correct locations?
-
Is the cabinet build quality acceptable, including earth bonds and back boards?
-
Is an earth electrode present where mains power is present, including power, circuit test and cert?
-
Is cabinet cable management & labelling and correct?
-
Are all taps and connections correct?
-
Is the cabinet correctly stencilled?
-
On Completion of works have the cabinets been left in a satisfactory condition and clear of debris?
9.0 CLOSE OUT
SIGNATURE
-
Signature: