Information
-
Audit No.
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 15
- N/A
-
Client / Site
-
FSAM
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 15
- N/A
-
Conducted on
-
Telstra Auditor
-
Contractor
-
Location
Audit Sheet
-
Audit Sheet
-
FSAM number.
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 15
- N/A
-
Site
-
SOR Code
-
Site Location
-
Activity
-
Audit
-
Audited Quantity
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 15
- N/A
-
Defect
-
Attribute
-
Add media
-
Defect Attribute
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
-
Defect Priority
-
Comments
-
Add media
-
Action Required
-
Defect Rectified
Conduit Installation Checklist
-
Conduit Installation Checklist
-
Reference Documents Pipe/ Conduit
-
1. Correct alignment obtained
-
Defect
-
Defect Status
-
Conduit and Pit Network Deployment
-
2. Correct depth achieved <br>
-
Defect
-
Defect Status
-
Deployment of the NBNCo Conduit and Pit
-
3. Correct separation from existing services
-
Defect
-
Defect Status
-
Under Ground Cable Installation
-
4. Correct conduit size and type used
-
Defect
-
Defect Status
-
Breakout Conduit labelling
-
5. No more than two 90 degree sweeping bends used in run
-
Defect
-
Defect Status
-
NBN-TE-CTO-490 Type 2 design doc
-
6. Bedding and support of conduits achieved
-
Defect
-
Defect Status
-
UNder Ground Direct Buried
-
7. Draw rope installed
-
Defect
-
Defect Status
-
Augmentation, Remediation and Build
-
8. Pipe entry to pit, placement & sealing to standard (min 50mm from bottom of pit)
-
Defect
-
Defect Status
-
9. Conduit plugs installed in empty conduits where required <br>
-
Defect
-
Defect Status
-
10. Split plugs, TDUX sealers <br>
-
Defect
-
Defect Status
-
11. Conduit Route markers installed to standard <br>
-
Defect
-
Defect Status
-
12. Where multiple conduits enter a pit, 25 mm minimum separation is required between each conduit<br>
-
Defect
-
Defect Status
-
13. Correct type of conduit used <br>
-
Defect
-
Defect Status
-
14. Bore log maintained and available <br>
-
Defect
-
Defect Status
-
15. Reducer joiner/spigot utilised where required for pit entry bore only<br>
-
Defect
-
Defect Status
-
16. Conduit attached to pole to standard <br>
-
Defect
-
Defect Status
-
17. Protective guard fitted to pole <br>
-
Defect
-
Defect Status
-
18. Site left safe <br>
-
Defect
-
Defect Status
-
19. Reinstatement to appropriate standard & rubbish removed <br>
-
Defect
-
Defect Status
-
20. Warning signs fitted where required
-
Defect
-
Defect Status
-
21. Check As built data (PIT location, GPS, etc.)
-
Defect
-
Defect Status
-
22. Installation meets all other design document specifications <br>
-
Defect
-
Defect Status
-
23. Breakout pipe sections are labelled to NBN-TE-CTO-1622
-
Defect
-
Defect Status
Enclosure Checklist
Joint Enclosure Installation Checklist
-
Conform to Design - LJL
-
1. Correct enclosure used
-
Defect
-
Defect Status
-
2. Conforms to Cable Splice design
-
Defect
-
Defect Status
-
3. correct pit utilised - (dependent on splice closure position & resultant cable loops)
-
Defect
-
Defect Status
-
4. minimum 15m length between pit wall and enclosure to allow withdrawal
-
Defect
-
Defect Status
-
5. Conforms to Splice Tables
-
Defect
-
Defect Status
-
Enclosure Tyco FIST Type 1 Architecture
-
6. all cable ties fitted are trimmed with no sharp points
-
Defect
-
Defect Status
-
7. Aluminium foil correctly positioned
-
Defect
-
Defect Status
-
8. correct position of ringbarked Hard Jacket / sheath
-
Defect
-
Defect Status
-
9. Inner edges of ports deburred before cable entry
-
Defect
-
Defect Status
-
10. cable sheath cleaned then abraded circumferentially to 100mm below port
-
Defect
-
Defect Status
-
11. cable ports cleaned then abraded
-
Defect
-
Defect Status
-
12. abraded materials cleaned off cable port and cable sheath
-
Defect
-
Defect Status
-
13. Heat shrink sleeves - correct kit used
-
Defect
-
Defect Status
-
14. non coated inner edge of heat shrink sleeve and or arrow pointed towards base of closure
-
Defect
-
Defect Status
-
15. green thermo indicating paint has been completely converted to black
-
Defect
-
Defect Status
-
16. heat shrink sleeve has not shrunk back more than 10mm from the base
-
Defect
-
Defect Status
-
17. Unused ports not scorched or damaged
-
Defect
-
Defect Status
-
18. proper adhesive flow shown around branch clip and or cable
-
Defect
-
Defect Status
-
19. central strength members (CSM) secured under the clamp
-
Defect
-
Defect Status
-
20. excess CSM length is cut away
-
Defect
-
Defect Status
-
21. enclosure labelled as per standard
-
Defect
-
Defect Status
-
22. cables labelled as per standard
-
Defect
-
Defect Status
-
23. cables enter enclosure as per local joint config
-
Defect
-
Defect Status
-
24. Spliced as per designed splicing table
-
Defect
-
Defect Status
-
25. splice tray config as per required layout
-
Defect
-
Defect Status
-
26. tray labelled as per standard with permanent marker
-
Defect
-
Defect Status
-
27. tray labelled on front of tray
-
Defect
-
Defect Status
-
28. fibre range & cable ID on side of tray where fibre wraps into splice
-
Defect
-
Defect Status
-
29. the bottom splice tray contains the first fibre/tube
-
Defect
-
Defect Status
-
30. spare fibres are coiled and secured under tabs around outside of the tray in a neat and orderly fashion
-
Defect
-
Defect Status
-
31. no unused fibres passing between splice tray holders
-
Defect
-
Defect Status
-
32. splice tray replaced on each tray and secured correctly onto back frame
-
Defect
-
Defect Status
-
33. all trays secured with supplied Velcro strap
-
Defect
-
Defect Status
-
34. desiccant bag has been removed from packaging and secured to the top tray with the Velcro strap or placed at the bottom of the enclosure
-
Defect
-
Defect Status
-
35. Fibre enclosure labelling correct, area code, cable number, fibre count, fibre number range, cable section identified
-
Defect
-
Defect Status
-
36. all sealing areas and sealing ring are clean before fitting dome
-
Defect
-
Defect Status
-
37. sealing ring fitted
-
Defect
-
Defect Status
-
38. sealing clamp secured
-
Defect
-
Defect Status
-
39. caution tape (warning, caution, hazard) applied e.g. clearly visible on a flat surface
-
Defect
-
Defect Status
-
40. enclosure sufficiently supported
-
Defect
-
Defect Status
-
41. site tidy no rubbish left on site
-
Defect
-
Defect Status
-
42. pressure tested as per spec
-
Defect
-
Defect Status
-
43. sufficient cable left in pit /MH - correctly housed
-
Defect
-
Defect Status
-
Asset Data Capture
-
44. Check As built data (spliced as per design) plus location on as built <br>
-
Defect
-
Defect Status
-
45. Item description captured correctly<br>
-
Defect
-
Defect Status
-
46. Other
-
Defect
-
Defect Status
Fibre Optic Hauling Checklist
Fibre Optic Hauling Checklist
-
1. Underground Cable Hauling
-
Cable Coiled neatly
-
Defect
-
Defect Status
-
2. Cable installed in correct duct <br>
-
Defect
-
Defect Status
-
3. Correct size cable installed<br>
-
Defect
-
Defect Status
-
NBN-TE-CTO-380 UG Cable Install
-
4.Fibre supported or housed to required standard <br>
-
Defect
-
Defect Status
-
NBN-TE-CTO-490 Type 2 Design
-
5. Cable maintenance loops installed as per design
-
Defect
-
Defect Status
-
NBN-TE-CTO-1364 Cable Coiling Guide
-
6. Bend radius not exceeded in looped cables
-
Defect
-
Defect Status
-
NBN-TE-CTO-379 direct buried
-
7. Sufficient cable length for enclosure housing etc
-
Defect
-
Defect Status
-
NBN-TE-CTO-378 MSS cable install Guide
-
8. If direct buried warning tape 300mm above cable / marker posts installed
-
Defect
-
Defect Status
-
NBN-COO-PD-003 Coding Structures for Physical Elements
-
9. Not cuts or damage in cable exposing fibres
-
Defect
-
Defect Status
-
NBN-NO-GDE-0002 Labelling guide
-
10. Is the correct kevlar hauling rope being used
-
Defect
-
Defect Status
-
11. End caps fitted <br>
-
Defect
-
Defect Status
-
12. Optical Fibre Cables labelled to specification <br>
-
Defect
-
Defect Status
-
13. Carrier notifications submitted (hauling over exist cables etc, check cables are not laced with other networks )
-
Defect
-
Defect Status
-
Reinstatement and Environment
-
14. Site left safe<br>
-
Defect
-
Defect Status
-
Asset Data Capture
-
15. Check as built data
-
Defect
-
Defect Status
-
16. Installation meets all other design document specifications
-
Defect
-
Defect Status
Pit Installation Checklist
Pit Installation Checklist
-
Reference Documents Pit Install
-
1. Correct materials used for pit foundation
-
Defect
-
Defect Status
-
NBN-TE-CTO-483 Conduit and Pit Network Deployment: Brownfield's
-
2. Pit/Manhole installed conforms to slope and ground level
-
Defect
-
Defect Status
-
NBN-TE-CTO-194 Deployment of the NBNCo Conduit and Pit
Network – Guidelines for Developers -
3. Correct depth, alignment & separation to other services
-
Defect
-
Defect Status
-
NBN-TE-CTO-380 UG Cable Installation
-
4. Correct size pit installed per design
-
Defect
-
Defect Status
-
NBN-TE-CTO-1622 Breakout Conduit labelling
-
5. Pit Gasket fitted
-
Defect
-
Defect Status
-
NBN-TE-CTO-490 Type 2 design doc
-
6. Pit not in driveways or hazardous areas
-
Defect
-
Defect status
-
NBN-TE-CTO-379 UG Direct Buried
-
7. Pit correct distance from roadway & corners
-
Defect
-
Defect Status
-
8. Pit not contorted due to over compaction
-
Defect
-
Defect Status
-
TIB-002Meaning of Augmentation, Remediation and Build
-
9. Bedding, backfill and compaction to standard
-
Defect
-
Defect Status
-
10. Centre bar installed
-
Defect
-
Defect Status
-
11. Pipe entry and PVC bush positioned and fitted to standard 50mm from bottom of pit for P50 & P100 Conduits, no side entry to pits.
-
Defect
-
Defect Status
-
12. Through conduits aligned inside pits<br>
-
Defect
-
Defect Status
-
13. Correct pit lid used with correct brand with weight stamped<br>
-
Defect
-
Defect Status
-
14. Cuts and holes sealed with approved repair kit - hole saw guide utilised & hole diam not excessive
-
Defect
-
Defect Status
-
15. Pit raised as per specs (risers sealed with plastic wrap/concrete) Screw spacing correct ; correct type or angle of screws.<br>
-
Defect
-
Defect Status
-
16. Pit fitted over existing plant as per spec
-
Defect
-
Defect Status
-
17. Telstra pits/ NBNCo id on cable/ Breakout pit sealed/ Collar rendered in concrete pit/ conduit labelled in breakout pit.. Subduct<br>
-
Defect
-
Defect Status
-
18. Site left safe
-
Defect
-
Defect Status
-
19. Warning signs fitted where required
-
Defect
-
Defect Status
-
20. Item description captured correctly
-
Defect
-
Defect Status
-
21. Check As built data (PIT location, GPS, etc.)
-
Defect
-
Defect Status
-
22. Installation meets all other design document specifications
-
Defect
-
Defect Status
-
23. Joint enclosure mounting bracket and MPT mounting bracket installed to Spec. (Best work practice to bolt during pit install)<br>
-
Defect
-
Defect Status
Red Pen Asbuilts Checklist
Red Pen Asbuilts Checklist
-
As Built Plan
-
1. cadastre ammendments captured
-
2. Bill of Materials verified against actual installation
-
Civils
-
3. symbology & format correct - ie bold red solid line, text bold black
-
4. FDH cabinet labelled correctly
-
5. pipe size / type corect & alignment shown. Depth of cover and offsets and /or chainage for differing offsets identified.
-
6. duct config correct
-
7. measurements between pits (centre to centre) correct to one decimal point
-
8. distances between blockages & pits captured
-
9. existing pit upgrade replacements captured
-
10. installed pipe as per design scope
-
11. breakout to aerial as per design
-
12. pit ID captured
-
13. Splice enclosure labelled correctly
-
14. multiport correct location
-
15. MPT number & port shown on design
-
16. Correct MPT utilised (4 / 8 port etc)
-
17. MSS cable detail captured
-
18. LSS -HSL cable detail captured
-
19. tethers hauled as per design
-
20. distribution cable hauled as per design
-
21. distribution cable labelled correctly
-
22. zone / AJL correct location
-
Aerial
-
23. pole number captured