Title Page
-
To be completed bu the H&S Adviser or Nominated person prior to the start of construction work on site. Audit reports shall form part of the CDM Health & Safety file.
-
Sensible Monitoring Audit Completed By:
-
Site Manager:
-
Contract Number:
-
Project Title:
-
Conducted on
Appointments
-
Any H&S actions identified shall be entered onto Audit / Inspection Action Log and brought to the urgent attention of the appropriate personnel as soon as possible. Contractor / Project Manager to be notified of actions required / taken.
-
1) What are the management arrangements for temporary works for the duration of the project?<br>(Procedures / Responsibilities / Design / Documentation etc.)
-
Comments:
-
Attach any images relevant to question 1 here.
-
2) Has a Temporary Works Coordinator been formally appointed?
-
Comments:
-
Attach any images relevant to question 2 here.
-
3) What minimum requirements have been established for the TWC's and TWS's?<br>(do the identify minimum requirements for competence experience, qualifications, knowledge & training)?
-
Comments:
-
Attach any images relevant to question 3 here.
Temp Works Schedule / Register
-
4) Has a register of temporary works been established and is the register being maintained in accordance with the clients procedures?
-
Comments:
-
Attach any images relevant to question 4 here.
-
5) Are all temporary works being undertaken on site (including temporary electrical supplies offices, workshop and equipment etc) identified on the Temporary Works Register?
-
Comments:
-
Attach any images relevant to question 5 here.
-
6) Have all temporary works on the register been categorized to identify required level of controls?
-
Comments:
-
Attach any images relevant to question 6 here.
Design
-
7) Has temporary works design been undertaken where specified on the register?
-
Comments:
-
Attach any images relevant to question 7 here.
-
8) Has the TW design been reviewed by a 3rd party (where required) and approved by the TWC?
-
Comments:
-
Attach any images relevant to question 8 here.
-
9) Do the RAMS for the works make reference to the TW design, plans and calculations (where applicable) to ensure correct implementation of the TW design?
-
Comments:
-
Attach any images relevant to question 9 here.
-
10) Has a temporary works supervisor been nominated for each area of work?
-
Comments:
-
Attach any images relevant to question 10 here.
-
11) Will regular temporary work inspections be undertaken as required by TWD / legislation and recorded?
-
Comments:
-
Attach any images relevant to question 11 here.
-
12) Are the temporary works being installed in accordance with the TWD (where applicable) and is a copy available at the workface?
-
Comments:
-
Attach any images relevant to question 12 here.
-
13) Is there a system in place for the review of temporary works for suitably following any change in condition i.e. excavations?
-
Comments:
-
Attach any images relevant to question 13 here.
-
14) Is there an inspection system for the monitoring of temporary works to confirm compliance?
-
Comments:
-
Attach any images relevant to question 14 here.
Sign Off Audit
-
Print Name:
-
Signature:
-
Project Manager Name:
-
Signature:
-
Designation:
-
Select date