Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
AV Cabinet
-
Are mounting blocks fitted?
-
Are cables terminated to patch panel?
-
Is the patch panel installed (by mounting to blocks)?
-
Is the RF Gateway installed?
-
Is the cresnet cable terminated and connected to RF Gateway?
-
Are the required aerial cables terminated and connected?
-
Is the ABAR installed and associated cables connected?
-
Is the Network Switch installed (by mounting to blocks) and connected?
-
Are all cables terminated for the Amp?
-
Is the Amp connected and installed?
Lighting Key Pads
-
Are all lighting key pads connected and installed?
iPod Dock
-
Is the iPod Dock connected and installed?
Touch Panel
-
Is the Touch Panel connected and installed?
TV
-
Is the RS232 connector terminated , back shell fitted and passed continuity test from AP2 (in the LCP) to TV?
-
Is TV installed and connected?
Photos
-
Please attach photos deemed necessary.
Items that require attention by third parties
-
Items required by third parties to complete.