Information
-
TNZ 47 Tank to Tank Transfer
-
Conducted on
-
Prepared by
-
Does this audit include all controls from the most recent hazard and risk register?
-
Are pre transfer checks made of ullage ?
-
Add media
-
Do two people confirm the receiving tank ullage is sufficient?
-
Add media
-
Is the area bunded?
-
Add media
-
Is automatic tank gauging in place and operational?
-
Add media
-
Are high level and high high level alarms in place and functional?
-
Add media
-
Is a physical check of at least receiving tanks level completed via GLI every 30 minutes ?
-
Add media
-
Is there a procedure in place for this process?
-
Add media
-
Is equipment used on a preventative maintenance schedule?
-
Add media
-
Are staff present throughout the transfer?
-
Add media
-
Is full PPE worn by staff involved?
-
Add media
-
Are all vapours discharged via tank vents ?
-
Add media
-
Is all equipment used earth bonded?
-
Add media
-
Is the Zone 0 hazardous area free from ignition sources?
-
Add media
-
Is the transfer line patrolled to confirm set up is and remains correct?
-
Add media
-
Is the area of the transfer including any hose or pipelines fully bunded ?
-
Add media
-
Is a Tier 1 Emergency plan available?
-
Add media
-
Have transfer hoses between inspected within 6 months?
-
Add media
-
Are all camlocks tied closed ?
-
Add media
-
Add any additional comments
-
Add any additional photos
-
List all corrective actions from this audit