Log On Site and ensure inclusion of the Working Party
-
Site Name:
-
On-site Wind Speed
-
Turbine Serial Number / ID
-
Inspector 1
-
Inspector 1 Proof
-
Inspector 2
-
Select date
Crane Pad and Access Roads
-
Are the access roads in good condition and free from standing water and vegetation
-
Photo of Approaching Track
-
Is there a suitable access route to the turbine base free from hazards
-
Photo of Access to WTG, Steps, Door, Immediate Ground
-
Is the crane pad in good condition and free from standing water and vegetation
-
Photo of Crane Pad
-
Additional information on Access and Ground Conditions:
-
Additional Photographic Information
Tower External
-
Is the turbine paint work in good order
-
Are the external flanges correctly sealed and painted
-
Are the access steps in good condition
-
Is the Access door in good condition
-
Additional information
-
Additional Information Media
Turbine Operation
-
Does the operation of the turbine sound Correct (yawing, pitching, blade noise)
-
Is The Turbine Operating Correctly Prior to Being Taken Out Service (STOP)
-
Additional information
-
Additional Information Media
Transformer
-
Is the transformer housing in good condition?
-
Is the area free from signs of oil leakage or strange rotten egg like smells coming from the housing?
-
Additional information
-
Additional Information Media
Internal Transformer and Switchgear
-
Is the transformer room secured from general access
-
Is the SF6 gauge within the green area
-
Is there a smell of rotten eggs (stop inspection immediately and contact site management).
-
Are the cables correctly laid
-
Are there any signs of damage, burning or heat stress to the cables of surfaces of equipment
-
Additional information
-
Additional Information Media
Lower Tower Internals
-
Is there an emergency action plan in the tower base?
-
Are the controls clearly marked in English and in good condition?
-
Are all cabinets only accessible by use of keys or tools?
-
Have the statutory inspections been completed for the ladder and fall arrest?
-
Photo of Ladder Tags
-
Are all electrical conductors suitably insulated?
-
Have the Statutory inspection been completed for the Anchor points in the tower
-
Is there a first aid kit in date?
-
Photo of First Aid Kit Contents
-
Is there a fire extinguisher of suitable type and in date? (CO2)
-
Photo of Fire Extinguisher in use
-
Is there a Climb Assist System in Place?
-
Make and Model of Fall Arrest System
-
Photo of Fall Arrest System
Bottom Cabinet A1
-
Is there a communication Link out available in the Tower Base?
-
Are there the correct Warnings Labels in clear site on the Cabinet (LV / HV)
-
Is there Cabinet Keys Available in the Tower Base?
-
Is the Q1 Breaker intact and Working Correctly?
-
Is the Q34 Breaker intact and Working Correctly?
-
Is the Q35 Breaker intact and Working Correctly?
-
Are all isolation capabilities intact and Working Correctly to all External Cabinet Isolation's?
-
Does the UPS Module Function Correctly?
-
How Often is the UPS Battery Changed?
- 6 months
- 12 months
-
Photos of the A1 Cabinet
Middle A4 Cabinet
-
Is there a Smoke Alarm Fittied Within the A4 Cabinet?
-
Are there the correct Warnings Labels in clear site on the Cabinet (LV / HV)?
-
Are all contactors / capacitors / fuses fully operational?
-
Is there any Smoke / Scorching damage to the cabinet?
-
Further Information on Cabinet Damage is applicable
Tower
-
Do the lights work (include test of emergency lights where possible)?
-
Are the tower cables correctly secured and free from damage?
-
Is the tower paint in good condition?
-
Are the bolt connections in good condition?
-
Are all fans and chutes correctly guarded/fitted?
-
Are all platforms and hatches in good clean working condition and secure?
-
Additional information
-
Photo of Platforms
-
Is the cable loop correctly installed and free from excessive twists?
Yaw Section
-
Do the lights Work (including test of emergency lights where possible)
-
Is the condition of the Twist Switch in good Working Order?
-
Does the Yaw Access Hatch Work Correctly and is in a secure State?
-
are the yaw teeth lubricated and showing even distribution of wear across the teeth face?
-
Are the yaw brake Pads free from Fraying?
-
Are the yaw gear oil levels correct and leak free?
-
Are the hydraulics free from leaks?
-
Additional information
-
Photographic Evidence of the Yaw System
Nacelle H&S
-
Is the rescue kit present, sealed and inspected?
-
Is there an emergency action plan in the nacelle?
-
Is there a fire extinguisher of correct type and in date?
-
Is there a First Aid Kit and is it in date?
-
Have all statutory inspections been completed?
-
Have the statutory inspections been completed on the crane and gantry?
-
Are all rotating parts sufficiently guarded?
-
Photo of the LS and HS Shaft Covers?
-
Are the controls in English and in good condition?
-
Are all cabinets only accessible by use of keys or tools?
-
Do the lights work (including test of emergency lights where possible)?
-
Are the Door Hinges free from cracks and corrosion?
-
Are all fans guarded and free from damage and corrosion?
-
Are the wind vane and anemometer free moving and in good condition?
-
MET Mast System Image
-
Are the hydraulic systems free from corrosion and leaks?
-
Hydraulic System Image
-
Additional information
-
Is the Nacelle Gutter Free from Water?
-
Is the Waste Collection Barrel empty and in a serviceable condition?
-
Additional Information Media
Generator
-
Does the generator run smoothly on the bearings?
-
Generator Status
-
Are all electrical connections in good condition
-
Are all Memolub Self Greasers functioning Correctly and are the pipes kink free?
-
Additional information
-
Are the Generator bed-plate Mounts in a GOOD serviceable Condition?
-
Generator Bed-plate Mount Image
-
Generator ID Plate Image
Gearbox
-
Is there a CJC Off-line Filtration System Fitted?
-
Is the CJC flow equal to 5mm or greater?
-
Which Service Does the CJC Filter Get Changed?
- 6 months
- 12 months
-
Is the On-line Filtration / Cooling System in GOOD Working order?
-
Is the condition of the cooling fan motor and fan in a serviceable condition?
-
Photo of cooling fan assembly
-
Are the rotor brakes (Low Speed Braking System) in good condition free from excessive dust and oil leaks
-
Are the rotor locks in good condition and free from leaks
-
Additional information
-
Additional Information Media
Blades
-
Is Blade A/1 in good condition
-
What Damage is in place?
-
Are all Vortex Generators intact?
-
Are all Stall Strips intact?
-
Is Blade B/2 in good condition
-
What Damage is in place?
-
Are all Vortex Generators intact?
-
Are all Stall Strips intact?
-
Additional information
-
Is Blade C/3 in good condition
-
What Damage is in place?
-
Are all Vortex Generators intact?
-
Are all Stall Strips intact?
-
Additional Information Media
Top A2 Cabinet
-
Are all Spare Signal Wires in the 50 Core available (Should be 10)?
-
Quantity Remaining:
-
Is Isolation Q21 in a good working order?
-
Additional Information on A2 Condition
-
Photo of any damage to A2 Cabinet and configuration
Retro-fit Systems
-
Is there a Memolub Auto-greaser system fitted to the hub?
-
What is the performance of the 4 auto-greaser capsules
-
Are there any other Retro-fits within the turbine?
-
Please enter details of any other retro-fit
-
Retro-fit Photo
-
Is the aviation light operating correctly and securely fitted
-
Is there an ice detection system operating?
-
Additional information
-
Additional Information Photo
Ancillary Systems
-
Additional Information on SYSTEMS / APPARATUS within the turbine
-
Additional images of Ancillary Systems
End of inspection
-
Has the turbine been returned to service
-
Is the turbine operating correctly
-
Has control been notified of return to operation
-
Turbine returned to operation
-
Auditors Signature