ISSUE
-
For any issues identified during this review, provide comments below the question, including any actions taken already, PER written (document PER#)
-
If a JSA WAS USED IN THE PRE-job briefing, did it adequately cover all of the hazards and control measures?
-
If a JSA was not used in the Pre-job briefing, did the Pre-job briefing checklist cover all of the hazards and control measures?
-
If a JSA was not used in the Pre-job Briefing, should a JSA be developed for this job?
-
Are there recommended changes to the work that could have improved the safe or efficiency of the work, I.e. PPE, work environment, tools, materials, equipment, etc.?
-
Were there any unexpected occurrences or a near miss during performance on the job?
-
Was the task accomplished with expected results?
-
Is any enhancement to work documentation warranted, I.e. we're procedures/step text complete and accurate, any print or schematic discrepancies, etc.?
-
Was planning and scheduling optimized to reduce the potential for human error?
-
Was material on hand and staged prior to beginning job.
-
We're lessons learned that change the way the job should be performed, recorded, passed on to others, and entered into MAXIMO as appropriate?
-
Did supervision provide the needed support and appropriate guidance when necessary?
-
Did you notice any human factor issues, improper or missing labels, or any significant physical hindrances to the performance of the work?
-
Did all workers have proper training needed or required to successfully and efficiently complete the the job?
-
Was the work area clean and housekeeping adequate?
-
Did all involved with the work understand their individual responsibilities?
-
Is additional follow up required from this POST-JOB Review.<br>( if YES, then the Foreman/Supervisor/Lead Performer is responsible to provide this feedback to the responsible group for action. )
-
NOTE: This form must be retained for 30 days or until work order/package is closed.
-
INTERVENTIONS:
-
NEAR MISSES:
-
LESSONS LEARNED:
-
ATTENDEES: