Rondo P140 Bottom Track.
-
Confirm the bottom track is fixed to the slab at 150 mm from the ends & 600 mm centres between.
-
Confirm that the bottom track has 6mm gaps between tracks to allow for moisture run out.
-
Confirm the fire acoustic sealant has been applied along the base of the Shaftliner Fire barrier on at least one side.<br>
Spacing
-
Confirm the cavity between the H-stud or I-stud and frame is in the range of 20mm - 40 mm.
-
Wall requires urgent rectification prior to proceeding. Take photos of issue.
-
Confirm H-Studs or I-Studs are full length pieces and not joined.
-
Wall requires urgent rectification prior to proceeding. Take photos of issue.
Aluminium Partiwall Clips
-
Confirm Aluminium Partiwall clips are fixed to every Partiwall stud directly, and not more than 3000 mm above lower clip line or base track.
-
Is it just one stud missing and Aluminium Partiwall clip, unable to install due to it being obstructed?
-
Take photos and forward to manager.
-
This is ok provided that the stud is clipped on the other side of wall. Take photo of item and move to next question.
-
Confirm Aluminium Partiwall clips have not been substituted with steel or other material.
-
Wall requires urgent rectification prior to proceeding.
-
Confirm H-studs or I-studs in roof cavity have 2 Aluminium Partiwall clips attached to roof framing.
-
Wall requires urgent rectification prior to proceeding.
Firestop
-
Confirm 16mm Firestop has been correctly laminated at 400 mm centres at floor/ceiling junction and in the roof cavity.
-
Urgent rectification required, must have laminating screws at maximum 400mm centres, vertically and horizontally.
-
Confirm 16mm Firestop laminated one side is not in contact with framing members.
-
Urgent rectification required, 16mm Firestop must not touch framing members.
Services
-
Are services located between framing and shaftliner fire barrier.
-
Urgent rectification required, service contact with partiwall will greatly reduce the acoustic performance of wall.
-
Confirm Shaftliner fire barrier is not penetrated other than by allowable penetrations in roof space.
-
Urgent rectification required, no penetration can be made in the wall.
-
Penetration is allowed provided a fire proof collar is fitted.
Insulation
-
Confirm Rockwool insulation is in place over ridge of wall and at wall ends.
-
Urgent rectification required.