Information
-
Substation Name
-
Project Manager
-
Project Title
-
Works Coordinator
-
Conducted on
-
Location
-
Network Number
-
PM Number
Overview
-
Brief Job Description
-
Sequencing
Stage
-
Discipline
- Substations
- UG Civils
- Overhead
- UG Jointing
- UG Test
-
Sequencing comments
-
Are Network Hours Acurate
-
Material Due Date
Civil Works
-
-
Number of Crews
-
Number of Days
-
Working Time
- Normal Time
- Over Time
-
Traffic required
-
Address and Number of crews
-
Plant and Equipment Required
- Backhoe
- Tipper
- Winch
- Jinker
- EPV
-
Contaminated Soil Identified
-
Additional Services
- Reinstatements
- Hydro
- NDD
- Rock Drill
- Borer
- Saw Cutting
-
Other Assets in Vecinity
- Gas
- Water
- Telstra
- Tramways/Rail
- Traffic Signals
-
Customers to be notified of Disruption due to Civil Work
-
Site Photos
Jointing Works
-
-
Number of Joiners
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
-
Days required
-
Working Time
- Normal Time
- Over Time
-
NAR Required
-
NAR Details
-
Operator
- Network Op
- Contractor LV Op
-
Traffic required
-
Address and Number of crews
-
EPV Required
UG Test
-
-
Number of Testers
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
-
Days required
-
Working Time
- Normal Time
- Over Time
-
SFT Required
-
SFT Details
-
Traffic required
-
Address and Number of crews
-
EPV Required
Other Site requirements
-
Customer Details
-
Site Comments
-
Pictures