Traffic Management
-
Ensure that all personnel are aware that the gas pipeline access corridor will serve as an alternative access/egress road that is designed for one way traffic and for light vehicles only.<br>
-
Notification
-
Public notification of progress and scheduling of works shall be undertaken so as to inform the community of any additional vehicles on the local road network.<br>
-
Stakeholders will be kept informed of works scheduling and any likely traffic related events for the project.<br>
-
Plan transport delivery and dispatch such as to avoid traffic flow interruption where practicable.<br>
-
Access to private property shall be maintained during construction unless otherwise agreed with the property owner in advance.<br>
-
Where traffic interruption is foreseeable, consult and inform neighbours of the event.<br>
-
Monitor and report to APA any incidents of damage or deterioration to public roads or easements associated with construction work activity.<br>
Operation of Vehicles and Plant / Machinery
-
Trucks will not queue up outside residential properties. No trucks will arrive on site or be permitted to queue near sensitive receivers prior to the 7:00 am start time unless required by road safety considerations.<br>
-
All vehicles regularly used for the Project will be maintained in good working order.<br>
-
Subject to safety requirements, trucks will not use exhaust brakes on site.<br>
-
Construction works would typically be undertaken between 7:00 am and 6:00 pm, seven days a week for 28 days and then 9 days off. One exception to this is the transportation of plant, equipment and pipe by oversized trucks outside of hours as required by authorities for safety reasons.<br>
-
Reversing of vehicles and equipment, and use of horns will be minimised to prevent noise emissions to nearby sensitive receivers.<br>
-
Where feasible and reasonable, replace “beeper” style reversing alarms with broad band variable level “quacker” reversing alarms or equivalent, ensuring that the OH&S legislation requirements are compiled with.<br>
-
Diesel vehicles used in construction will be fitted with spark arresters.<br>
-
Prior to clearing and grading, all vehicles entering the ROW will undergo washdown in established quarantine zones to minimise weed spreading risks.<br>
Air Quality
-
Locally produced goods and services would be procured where feasible to reduce transport fuel emissions.<br>
-
All vehicles and equipment will be regularly serviced, as per manufactures instructions and maintained in proper working order.<br>
Geology and Soils
-
Only certified clean bedding and padding materials will be imported for laying around the pipe. Any imported fill material will be sourced from a reputable (preferably local) supplier, be weed and disease free and have a letter or certification from the supplier showing it has been sourced from approved natural quarry materials. A copy of the weed and disease free statement, certification from the supplier showing it has been sourced from approved natural quarry materials is to be kept on file.<br>