Title Page

  • Site ID No

  • Site

  • AM Responsible

  • Date Inspected

  • Inspected by

  • Role / Position

QOS Inspection

Last Service Information

  • Last Service Date

  • Performed by (Company)

  • Work Order

  • Work Instruction / Form

Last Reactive Maintenance information

  • Last RM Date

  • Performed by (Company)

  • Work Order

  • Work Performed

Inspection Checks

  • Is evidence of the last PM attendance registered in the Site Entry Log?

  • Add media

  • Is evidence of the last RM attendance registered in the Site Entry Log?

  • Add media

  • Are log books present and are entries consistent with the current expected PM program for each of the following systems:
  • Fire Indicator Panel & Evacuation System(s)?

  • VESDA systems?

  • Fire Pump sets?

  • Gas Detection systems?

  • Stairwell pressurisation systems?

  • Hydrant / Sprinkler systems?

  • Fire Doors?

  • Emergency and Exit lighting?

  • Add media

  • Are any significant visible/audible plant / fire equipment defects recorded in the log records?

  • Add media

  • After reviewing the equipment service logs/histories is the history clear and traceable for each system?

  • Add media

  • Have Work Orders / SWIM entries been registered to capture & trigger follow up of any current Alarms or Faults observed or recorded in the log books?

  • Add media

  • Where equipment is currently tagged out of service or shut down do “Out of Service” tags (or Warning Tags) clearly indicate the date, reason and contact point for information regarding the shut down?

  • Add media

  • Have Fire Impairment Notifications been received and approved for any fire detection / response system isolations that are in place?

  • Add media

  • Are Fire Pump Auto / Manual and Lead / Lag controls set for normal operation (or tagged and noted in the log book where abnormal operation has been deemed necessary)?

  • Add media

  • Are Fire Extinguishers, hose reels and hydrants within test date (serviced sites only)?

  • Add media

  • Were all observed Exit and Emergency lights illuminated?

  • Add media

  • Has Maximo been updated to capture any apparent new / changed Fire detection / response equipment at the site?

  • Add media

  • Have changes to PM routines been recommended / adopted to reflect any apparent new / changed Fire detection / response equipment?

  • Add media

  • General Comments / Issues

  • Auditor: Register the completed audit in the Issues, Incidents and Audits SharePoint register. Enter any actions that warrant capture and/or follow up in the Actions register.

    Issue Escalation
    • Report on any urgent defects or safety hazards to Telstra P&FM: 1300 652 235.
    • If the contractor performs work in a way that there is an immediate threat to people’s safety, the network or the environment the contractor must be advised to stop work and the Area Manager and nominated Contract Coordinator must be informed.
    • Incidents and hazards must also be escalated to Visionstream / Client contacts and, where applicable, Incident Reports / Hazard Alerts created and distributed in accordance with the Incident Actions Ready Reckoner (VS(NIFM)-FO-PIN-095).

  • Inspector sign off: This is a true and accurate reflection of the state of the above site. All contractor non-conformance's, maintenance requirements and any other potential problems observed have been reported.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.