Title Page
-
Site ID
-
Site
-
AM Responsible
-
Date Inspected
-
Inspected By
-
Role/Position
QOS Inspection
Last Service Information
-
Last Service Date
-
Performed By (Company)
-
Work Order / NSLog
-
Work Instruction / Form
Last Reactive Maintenance Information
-
Last RM Date
-
Performed by (Company)
-
Add media
-
Work Order / NSLog
-
Work Performed
Inspection Checks:
-
Is evidence of the last PM attendance registered in the Site Entry Log?
-
Add media
-
Is evidence of the last RM attendance registered in the Site Entry Log?
-
Add media
-
Are Battery books on-site for each Battery String?
-
Add media
-
Are the results from the last Battery Discharge test performed correctly recorded in the Battery book for each string?
-
Add media
-
Is other Battery Book information consistent with the current condition of each string (e.g. DoM, date installed, defective cells recorded, etc.)?
-
Add media
-
Are results from the last Conductance Test correctly recorded in the Celltraq database?
-
Add media
-
Have the Audit Stickers been updated for each Power ID to record the last PM performed?
-
Add media
-
Have Work Orders / SWIM entries been registered to capture & trigger follow up of defective cells?
-
Add media
-
After reviewing the Battery Record books, is the history of each string clear and traceable (including any new information regarding battery condition from RM attendances (e.g. String failed after x hours))?
-
Add media
-
Is the Maximo battery data, including current capacity, consistent with the batteries on site and the information in the Battery Books?
-
Add media
-
Are batteries, terminals and battery shelves free from excessive salt / electrolyte build up?
-
Add media
-
Are solar cells (if present) clean and clear of shade from over hanging vegetation?
-
Add media
-
Where equipment is currently tagged out of service or shut down do “Out of Service” tags clearly indicate the date, reason and contact point for information regarding the shut down?
-
Add media
-
Are Battery Rooms free from maintenance waste?
-
Add media
-
Are any spare parts / materials present labelled and stored correctly?
-
Add media
-
General comments/ issues:
-
Auditor: Register the completed audit in the Issues, Incidents and Audits SharePoint register. Enter any actions that warrant capture and/or follow up in the Actions register.
Issue Escalation
• Report on any urgent defects or safety hazards to Telstra P&FM: 1300 652 235.
• If the contractor performs work in a way that there is an immediate threat to people’s safety, the network or the environment the contractor must be advised to stop work and the Area Manager and nominated Contract Coordinator must be informed.
• Incidents and hazards must also be escalated to Visionstream / Client contacts and, where applicable, Incident Reports / Hazard Alerts created and distributed in accordance with the Incident Actions Ready Reckoner (VS(NIFM)-FO-PIN-095). -
Inspector sign off: This is a true and accurate reflection of the state of the above site. All contractor non-conformance's, maintenance requirements and any other potential problems observed have been reported.