Title Page
-
Conducted on
-
Prepared by
-
Location
-
Project:
-
Client:
-
Contractor:
-
Site conditions:
-
Are TTM's in place and in accordance with plans?
-
Is correct PPE being used?
-
Are open trenches protected using bunting, fencing or similar?
-
Are trenches over 1.5m benched, battered or are shoring boxes in use?
-
Are materials being stored safely?
-
Are there any other safety concerns? If so detail, photograph and assign actions. Note: If there is an immediate risk to a persons safety then instruct the works to stop and contact the person in charge as well as Spiire construction team.
-
Environmental
-
Is contractor working in accordance with the approved EPA drawings?
-
Is dust being suppressed during excavation and backfilling of trenches?
-
Are there any other concerns regarding Environmental issues? If so detail, photograph and assign actions.
Trench Excavation
-
Does trench width conform wit Icon Water Standards and design drawings?
-
Is there any ground water present in trench? If so please detail method used for bedding and haunch and photograph.
-
Is base free from rocks and loose material?
Pipe installation
-
Are the correct revision of drawings being used by the contractor?
-
Does bedding material conform with Icon Water Standards? If so sight site specific grading certificate.
-
Are pipes and fittings all compliant with Icon Water approved products list and have they been inspected by inspector?
-
Have all SV's been signed off by Icon Water inspector?
-
Are water services installed as per design, in correct location and at correct depth?
-
Is road sub base material approved and passing grading requirements? If so sight grading certificate.
-
Is select material free form organic material and particles greater than 75mm?
-
Has tracer wire been installed and wrapped around hydrant springer head 3 times?
Finals
-
Have compaction tests been done on trench backfill and do they comply with compaction requirements?
-
Has water main pressure testing passed? Take a copy of compliance certificate and ensure serial number matches.
-
Are water services all 600mm +/- 50mm into the boundary, finishing flush with FSL and sleeve is in tact?
-
Are hydrant and SV boxes finishing flush with FSL and centred over fitting?
-
Are kerb and road markers in place and correct?
-
Are block boundary pegs in place to allow for final water inspection?
-
Comments: