Information

  • Company

    no label
  • Weld Clad Quality Audit Building 1

  • Conducted on

Auditor

  • Auditor Role

1.0 Weld Equipment

  • Select Weld Rig

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

2.0 Work Order and Information

  • Enter Work Order Number

  • All previous Ops signed off

  • Detail the Operations not signed

  • Take photo of Work Order page showing the unsigned Op(s)

  • Is a Weld KanBan available with the Work Order?

  • Provide a reason

  • Has the Release KanBan been placed in the release section of the main KanBan board?

  • Provide a reason

  • All previous welded details buddy checked and sizes signed off?

  • Provide a reason

3.0 Welding

  • Enter the WPS being used

  • Enter Welder Name & Number

  • Is the welder's coding approved for the WPS stated?

  • Detail any job specific issues

4.0 Visual Management & W.I.P Count

  • Is the metrics board up to date?

  • Take photo of the metics board

  • Enter the number of parts in the weld shop (Supermarket / Weld / Stress)

  • Enter the number of tickets detailed on the WIP board.

  • Does the number of parts match the number of tickets on the board?

Sign Off

  • Auditor's signature

  • Witness

Weld Equipment

  • Select Weld Rig

  • Is there any equipment specific issues?

  • Has a Maintenance request been created?

  • Detail the Weld Rig Specific Issues

  • Equipment Within Calibration

  • Take photo of Calibration Sticker and / or Certificate

1. Work Order and Information

  • Enter Work Order Number

  • All previous Ops signed off

  • Detail the Operations not signed

  • Take photo of Work Order page showing the unsigned Op(s)

  • Is a Weld KanBan available with the Work Order?

  • Provide a reason

  • Has the Release KanBan been placed in the release section of the main KanBan board?

  • Provide a reason

  • Correct Drawing Visible?

  • Provide a reason

  • All paperwork correct to Part Report?

  • Provide a reason

  • All previous welded details buddy checked and sizes signed off?

  • Provide a reason

2.0 - Material Type

  • Select the material being Welded

3.0 - Filler Material

  • Select the filler material type being used

  • Enter filler material batch number

  • Take photo of batch number (if accessible)

4.0 - Welding

  • Enter the WPS being used

  • Are the correct WPS parameters being used?

  • Take photo of Weld Parameters

  • Enter the correct program name to be used on the part detail

  • Has the correct program been selected?

  • Provide a reason

  • Take picture of program Macros

  • Detail any job specific issues

Sign Off

  • Auditor's signature

  • Witness

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.