Title Page
-
Site conducted
-
Conducted on
-
Account used
-
Property Address
Health & Safety
-
Is health & safety on site acceptable? ie Correct PPE being worn, Rams signed ?
-
Are there any Gas flues present, have they been isolated, Tagged and a permit to work been issued by Equans ?
-
Has an Asbestos survey been conducted ? List any actions.
-
Has the Scaffold been inspected, Handed over and tagged ?
Housekeeping
-
Is the site, material storage and our working areas tidy and organised.
Weekly Labour levels
-
Please confirm Labour levels on site inc site management & Labourers
Weekly Weather
-
Please list general weekly weather & any lost days due to bad weather
Site Instructions
-
Have any site instructions / variations or requests been issued
Procurement
-
Are all materials on site
- Tiles 100 %
- Batten & Membrane 100%
- Lead 100 %
- Fascia , Gutter & Downpipes 100 %
- All ancillary items 100 %
QA
-
Additional insulation required and installed to loft ?
-
Batton fixing specification adhered to?
- Yes
- No
- N/A
-
Fascia over Vent installed?
- Yes
- No
- N/A
-
Membrane support tray/ 5u installed?
- Yes
- No
- N/A
-
Roll out rafter tray installed?
- Yes
- No
- N/A
-
Membrane installed to specification?
-
RWA45 Firewall insulation installed?
- Yes
- No
- N/A
-
Tiles fixed to manufactures specification?
- Yes
- No
- N/A
-
First & last ridge additional fixing ?
- Yes
- No
- N/A
-
Headlap suitable for pitch tile type
- Yes
- No
- N/A
-
Fascia , Gutter & Downpipe installed correctly?
-
Leadwork installed correctly ? This includes Chimneys and wall abutments
Completion
-
Are there any other notes relevant to these works?
-
Sign below
-
Russell Roofing Signature
-
Equans Signature