Title Page
-
Conducted on
-
Location of QA
-
Photos of location
-
Prepared by
QA Inspection
Tyvek
-
Has the Tyvek house wrap been installed
-
Has the correct double sided tape been used
-
Has the correct amount of overlapping been applied
-
is the over lap the correct way round top over bottom
-
Has the correct acrylic tape been applied to all joints
-
Is the Tyvek free from damage
-
Date & Time of inspection
-
Inspected by
-
Photo of elevation
TOP HATS
-
Has the correct top hat been installed
-
Has the top hat been installed to the correct centre's
-
Has the top hat been fixed to the SFS studs
-
has the correct fixings been used
-
Has the top hat been installed to the correct Hight & Level
-
Date & time of inspection
-
Inspected by
-
Photo of elevation
Helping Hand Brackets
-
Have the correct helping hand and brackets been used
-
Have the helping hands been set out correct as per design
-
Have all brackets been installed correct as per design
-
Have the correct fixings been used as per design
-
Has the horizontal bracket been installed
-
Has the horizontal brackets been fixed as per design
-
Has the correct slots and dead fix positions been used on the brackets
-
Date & Time of inspection
-
Inspected by
-
Photo of elevation
Fire stops HOLD POINT
-
Has the correct FSI vertical fire barriers been installed
-
Are the vertical FSI fire barriers installed correct 2 fixings centers per 1000mm piece
-
Have the retaining brackets been inserted 75%into the vertical fire barrier and has made intimate contact with substrate
-
Have all vertical fire barriers been tightly abutted
-
Is the vertical fire barriers under the correct compression minimum 5-10mm
-
Has the foil tape been applied to all joints and corners, internally & externally
-
Has foil tape been applied to all abutted joints and not covering the Intermescent strip
-
Has the correct FSI specification horizontal fire barriers been installed
-
Have the horizontal retaining brackets been installed 3 brackets per 1000mm piece fixed at 250mm, 500mm and 750mm centers
-
Have the horizontal fire barriers been installed with intimate contact with substrate
-
Have the horizontal fire barriers been installed tightly between all brackets
-
Has the required open cavity been achieved
-
Has the pig tails been installed correct and at the correct centers
-
Date and time of inspection
-
Inspected by
-
Photos of elevation
Insulation
-
Has the correct spec insulation been installed
-
Has the insulation been abutted to each other with no visible gaps
-
Has the insulation been installed with intimate contact with substrate
-
Has the insulation been cut tightly around bracket penetrations
-
Has the correct fixings been used
-
Is the insulation free from damages
-
Date and time of inspection
-
Inspected by
-
Photos of elevation
Horizontal & Vertical rails
-
Has the correct Horizontal rail been used
-
Has sufficient fixings been installed to the horizontal rails
-
Have the correct dead fix and elongated holes been used
-
Has the correct Brick slip rails been used
-
Has the brick slip rails been fixed correct
-
Are all rail correct as per grid line and datum
-
Are all rails lined and level
-
Are brick slip channels free from bends / damage
-
Has sufficient fixings been installed to the brick slip rails
-
Has the setting out been followed as per design
-
Date & Time of inspection
-
Inspected by
-
Photos of elevation
Brick slips
-
Has the correct type of brick been installed
-
Are the bricks sitting in the channels correct
-
Are the bricks lining up with each other
-
Are the bricks flush with each other
-
Has the correct pattern been followed
-
is the bricks slips free from damage
-
Has the correct gap between each slip been maintained 10mm
-
Has the correct mortar been applied and fully imbedded
-
Has the movement joint been maintained
-
Date & Time of inspection
-
Inspected by
-
Photos of elevation