Title Page
-
Conducted On
-
Inspectors Name
-
Location
-
Name of site foreman/supervisor
Untitled Page
-
Is the Vehicle parked safely & legally?
-
Condition of exterior
-
Condition of tyres
-
Condition of interior including cleanliness
-
Safety barriers and hazard warning signs displayed where appropriate?
-
Suitable Fire Extinguisher kept onsite?
-
Fire Extinguisher free from damage/defects & displaying a valid service sticker (serviced within the last 12 months)?
-
Fully stocked First Aid kit including eye wash kept onsite?
-
Are all items in date?
Tools & Equipment
-
All tools and equipment free from damage and in good working order?
-
Are tools suitable for the tasks undertaken e.g. VDE standard tools when working with electricity?
- Yes
- No
- N/A
-
Tools such as the Stanley Trimming Knife include self-retracting blades?
-
All electrical tools & equipment received PA test within the last 6 months?
-
Access equipment such as ladders and hop-ups free from damage/defects and suitable for the task?
-
All access equipment including ladders and hop-ups displaying a valid inspection sticker (inspected within the last 3 months)?
-
Suitable hatch covers used where floorboards have been removed?
PPE
-
Hi-Vis being worn correctly and in acceptable condition?
-
Suitable safety boots worn correctly and in acceptable condition?
-
Hard hat worn when required and in acceptable condition?
-
Suitable RPE worn when required (e.g. When handling hazardous materials/substances or drilling into brickwork)?
-
Suitable gloves worn when handling hazardous products/substances?
-
Cut resistant gloves (L5) worn when using tools such as the Stanley Trimming Knife?
-
Suitable safety glasses worn when required (e.g. When handling certain hazardous substances, drilling into brick work etc)?
H&S Documentation
-
All required site documentation available including: Risk assessments, method statements, COSHH assessments, Incident reporting procedures and asbestos reporting procedures?
-
Permit to work system adopted where required?
-
Site register available and filled out correctly?
-
Construction phase plan and asbestos survey report available to site team where required?