Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Please insert construction plan drawing of the project with assigned numbers to each elevation. (See point 3 of the reporting Rules)

  • BEFORE YOU START THIS REPORT, REFERENCE MUST BE MADE TO THE PROJECT ELEVATION LAYOUT SKETCH DETAILING THE EXACT LOCATION(S) INSPECTED.

    Rules of WIR and Progress Reporting:

    1. All reports need to be in for the dates that have been agreed on the Reporting Schedule. PM must contact HSEQ Department if there will be a delay.
    2. The elevation inspected must be clearly identified using the Elevation Layout Sketch produced by the CM of the project, clearly identifying each elevation and floor. Ideally, there should be a separate Report for each elevation, however on smaller works, a single report for more than one elevation is acceptable.
    3. Each report should include a description of the type of system / works undertaken.
    4. Reports should also include quality issues not caused by CF, but which impact on our works.
    5. Refer to recent Supplementary Quality Reports before starting.
    6. We have issued standard Detail drawings reference numbers D01, D02, and so on. These need to be referred to throughout WIR and clearly show what is required. Only “Clarke” Drawings should be followed.
    7. All reports must be up-loaded to Clarkes Server or emailed to HSEQ Dept before deadline.The next report that will follow must show how the errors were rectified. If improvement was not possible, e.g.: due to soft ground/lack of access, it needs to be described/explained. The answers column still needs to be highlighted red. However, if the error was rectified the section should be changed to green. The comment section is to be used for explanations of how and when error was rectified.
    8. If project manager has found an error during the assessment, it must be noted and fixed before consecutive stages of works progresses, eg: CP board cannot start before Metsec sub frame is properly fixed. Quality Control Manager cannot accept the next WIR report until everything is fixed and up to date on the previous report. This is to make sure that all errors are corrected, and there are no error omissions.
    9. Reports need to be genuine and relevant.
    10. It is important that reports always have any delay events recorded.
    11. All completed reports must be sent to head office, client and subcontractor.





  • Has the appointed sub-contractor read, understood and been given a copy of relevant parts of WIR?<br>

  • Elevations assessed & works completed

  • Add media

  • Completed by subcontractors.

Breather Membrane & EPDM

  • 1. Has the EPDM been fitted properly at CP Board and concrete interfaces, is there a strong bond with substrate, EPDM edges sealed with adhesive and no bubbling?<br><br><br>

  • Add media

  • 2. Has the correct and specified breather membrane been installed?<br><br>

  • Add media

  • 3. Has the breather membrane been dressed out and over horizontal flashings / pods, taped and sealed?<br><br>

  • Add media

  • 4. Has breather membrane been taped fully at vertical joints and overlapped 300mm at horizontal joints?<br><br><br>

  • Add media

  • 5. Has the breather membrane been taped to and around all openings protrusions, as specified on the Reference Drawing D 03 (see MClarke reference booklet)<br><br>

  • Add media

  • 6. Has interface between Roofing Membrane & Breather Membrane been sealed with Dafa tape?<br><br><br>

  • Add media

Support frame fitted into concrete.

  • 1. Have helping hand brackets been installed in accordance with the sub frame layout drawings?<br><br>

  • Add media

  • 2. Have specified brackets with thermal pads been fitted to the substrate at specified fixing centres ? <br>

  • Add media

  • 3. Have helping hand brackets been fixed to concrete substrate with one anchor.?<br>

Insulation between brackets.

  • 1. Has there been correct insulation type and thickness installed?<br><br>

  • Add media

  • 2. Has proper pattern of mechanical fixing been used ?.(Reference, see Figure 7, M.Clarke Guidance Booklet.)<br><br><br>

  • Add media

  • 3. Have fire pins been installed minimum one per board?<br><br><br><br>

  • Add media

  • 4. Has insulation been fitted as tight as possible to the board / substrate and up to next insulation board ?<br><br><br><br>

  • Add media

  • 5. Have all outlets, brackets, vents, edges of insulation boards, joints etc. been taped up with silver tape?<br>

  • Add media

Rails fitted into helping hand brackets.

  • 1. Has the correct type of rail been used (there are two different types- longer rails are to be fitted around the window opening)?<br><br><br>

  • Add media

  • 2. Has there been specified number of brackets per rail length used?<br><br><br>* 0 - 1.55m long rail requires 1 double fixed points bracket & 1 single floating point bracket.<br>* 1.55m - 2.15 m rail requires 2 double fixed point brackets & 1 floating single bracket.<br>* 2.15m - 3 m rail requires 2 double fixed point brackets & 2 floating point single brackets.<br>* 3m - 3.85 m rail requires 2 double fixed point brackets & 3 floating point single brackets.<br><br><br><br><br>*1.55m - 2.15m

  • Add media

  • 3. Have L/T shape rails been fitted to the brackets through the specified holes so as to create fixed and floating fixing points as and where required?<br><br><br>

  • Add media

  • 4. Have rails been set in accordance with deflection point locations with specified deflection gap 10mm between them ?<br><br><br>

  • Add media

  • 5. Have rails been set accurately with rotating laser?<br><br><br><br>

  • Add media

  • 6. Has the Project Manager checked the plumb / level with string line or laser?<br><br><br><br>

  • Add media

  • 7. Have correct type and number of fixings been used on brackets? <br><br><br><br>

  • Add media

  • 8. Is the top and bottom of the rails overhanging no more than it is indicated on the rail setting drawing?<br><br><br><br>

  • Add media

  • 9. Has there been gap maintained in rails along the horizontal movement joints?<br><br><br><br><br>

  • Add media

SFS To soffits. (No Drawings/TBC)

  • 1. Have the SFS been given status and passed by the architect?<br><br>

  • Add media

  • 2. Has the operative been given the relevant drawings and details to complete the works.?<br>

  • Add media

  • 3. Has the Main Contractor signed off datum and gridlines settings, are gridlines visible?<br>

  • Add media

  • 4. Is the wall constructed using the correct depth and gauge of studs/trucks?<br>

  • Add media

  • 5. Are operatives using the correct track fixings? Are the tracks fixed/installed to concrete/steel at correct centres?<br>

  • Add media

  • 6. Have track fixings been fixed at min 50mm edge distance.?<br><br>

  • Add media

  • 7. Are the operatives using the correct 'tek' screws for installing studs?<br>

  • Add media

  • 8. Have the studs been installed to suit cladding joints locations?<br><br>

  • Add media

  • 9. Has the wall been set out to the correct Gridline offset? In the correct location?<br>

  • Add media

  • 10. Have the compound sills and lintels been fixed together at centres of no more than 300 mm?<br>

  • Add media

  • 11. Have the openings been formed in the correct locations? At correct height, length and width?<br>

  • Add media

  • 12. Are the openings being formed using the correct studs/tracks compounds as per approved design specification?<br><br><br>

  • Add media

  • 13. Have lintels been fixed to studs as per Metsec standard detailed drawing?<br>

  • Add media

  • 14. Have deflection heads been installed correctly with the required movement allowance?<br>

  • Add media

  • 15. Have the works been completed to the current outline specification and manufacturers specification? (including windows and doors openings)<br>

  • Add media

  • 16. Have the works been completed to current revised SFS drawings and details?<br>

  • Add media

  • 17. Has the deflection gap been maintained at 15 mm. ?<br>

  • Add media

  • 18. Have SFS angles been fixed to concrete with 1 No of 4H32 Tapcon Anchor at all studs locations.?<br><br>

  • Add media

  • 19. Is the wall completed to a true line and level?<br>

  • Add media

CP boarding and sealing.

  • 1. Has board of specified type and thickness been installed?<br><br>

  • Add media

  • 2. Are there 3mm gaps around all edges?<br>

  • Add media

  • 3. Has there been a 15mm gap left for floor deflection joints ?(Drawing Reference: D01, see MClarke reference booklet)<br>

  • Add media

  • 4. Have the screws been fixed correctly (not over tight) into boards, using Nose Piece?(Drawing Reference: D02. See MClarke reference booklet)<br>

  • Add media

  • 5. Have the correct number of fixings(minimum of 25/at 300mm centres) been installed to each board? <br><br>

  • Add media

  • 6. Where necessary, Has CP Board been fitted with smooth face outside and textured face internally?<br>

  • Add media

  • 7. Has the CP board been installed with no bumps, gaps, and bows?<br>

  • Add media

  • 8. Was Daffa tape and RCM Compound (enough to nearly hide the writing) been applied to all CP Board joints?<br>

  • Add media

  • 9. Has the EPDM been installed to deflection joints and/or concrete interfaces?<br>

  • Add media

Window pods.

  • 1. Have window openings been checked for centring and plumb prior to installation ?<br>

  • 2. Have Windows Pod Flashings been joined correctly with female and above male end?<br>

  • 3. Is gap between window jam/pod and brick 15mm (+/-2mm) ?<br>

Corium brick system.w

  • 1. Has perforated flashing been used at base?<br>

  • Add media

  • 2. Has horizontal expansion been maintained at every 9m, and vertical at 10m ?<br><br><br><br>

  • Add media

  • 3. Have Corium rails been fitted to the sub-frame rails with specified number of stainless steel fixings (18nr/m2) and Neoprene washers at correct centres? (Layout sketch must be followed)<br><br><br><br><br><br><br><br>

  • Add media

  • 4. Have rows of profiled steel sections been interlocked vertically?<br><br><br><br>

  • Add media

  • 4. Has White Mallet been used to tap in brick?<br><br><br><br>

  • Add media

  • Add media

  • 6. Have window measurement been checked for gridline alignment?<br><br><br><br>

  • Add media

  • 7. Have gaps between windows been set to allow fitting 3 nr of brick slips?<br><br><br>

  • Add media

  • 8. Have the bricks been securely clipped into place as shown by manufacturer ?<br><br><br><br><br>

  • Add media

  • 10. Have there been proper spacers used between brick slips ?<br><br><br><br><br>

  • Add media

  • 11. Have critical dimensions of 890mm from edge of brick to edge of fourth column of brick been maintained?<br><br><br>

  • Add media

  • 12. Has the weather been checked before planned application of the pointing mortar?(this is of utmost importance as rain can stain brick slips)<br><br><br>

  • Add media

  • 13. Is the quality of brick good, can the mortar be applied to the brick joints? <br>It is important to check the weather forecast before pointing as rain may dissolve the pointing and stain brick slips)<br><br><br><br><br>

  • Add media

  • 14. Has the pointing mortar been mixed with the specified amount of water?<br><br><br>

  • Add media

  • 15. Has mortar been allowed correct time to cure before pointing was finished.? (Mortar to be left for 2-4 hrs., Snots have to be taken off immediately after)<br><br>

  • Add media

  • 16. Has the water from between brick joints been blown out with air line?<br><br><br><br>

  • Add media

  • 17. Has metal swarf been removed from between the rails so as to eliminate rusting risk?<br><br><br>

  • Add media

  • 18. Has the brick been cleaned from the excess of pointing mortar before fully curing ?<br><br><br><br>

  • Add media

  • 19. Have all bricks been washed down, is it presentable for the Client to snag.?<br><br>

  • Add media

Trespa Panels

  • 1. Are drill holes in Trespa panels 10mm, with exception for one hole in the middle of the panel, which must be 5.1 mm (fixed point)?(It is recommended to use 4mm pilot hole first)<br><br><br><br><br>

  • Add media

  • 2. Are drill holes in rails 5.1 mm diameter to take 5mm rivet ? IS centralising tool being used ?<br><br>

  • Add media

  • 3. Has the gap between rivet head and the panel been maintained at distance of 0.3-0.5mm using Nose-piece on rivet gun ?<br><br>

  • Add media

  • 4. Have rivets been fitted at consistent distance of 25 mm(+/- 2mm) from the edge of the panel?<br><br><br><br><br>

  • Add media

  • 5. Have Trespa panels been held tight against rails during fixing stage, especially at facets?<br><br><br><br>

  • Add media

  • 6. Has fire break been maintained away at correct distance from Trespa panel(as per assessed project/drawing)?<br><br>

  • Add media

  • 7. Has Flymesh been fitted at base and at cill location?<br><br><br>

  • Add media

  • 8. Has trespa sub-frame been blacken-out/shadowed to hide it.?<br><br><br>

  • Add media

  • 9. Are there equal spacing of 10mm between Trespa panels. Has 10mm gap-stick been used to check spacing?<br><br><br>

  • Add media

  • 10. Have panels been cleaned on completion?<br><br><br>

  • Add media

Insulated render.

  • 1. Has the applicator been given all detail drawings, levels, locations of firebreaks and expansion beads?<br><br>

  • Add media

  • 2. Has the applicator been given information of what way the adhesive is applied to board(dabs, grated trowel or picture frame).?<br>

  • Add media

  • 3. Have all down pipes, vents, grounds, brackets etc. been installed on the wall and properly sealed?<br>

  • Add media

  • 4. If permanent cappings are not in place, are temporary cappings on?<br>

  • Add media

  • 5. Have insulation boards been additionally fixed to the substrate with proper number of mechanical fixings( as per design/manufacturer specification)?<br><br>

  • Add media

  • 6. Have insulation boards been fitted to the wall so as to achieve even surface.?<br><br>

  • Add media

  • 7. Have installers used plumb line for the surface line monitoring when fitting insulation boards?<br>

  • Add media

  • 8. Have all door frames and window frames been over lapped by insulation at a minimum of 10 mm in order to ensure of good sealing?<br>

  • Add media

  • 9. Has the insulation been flag cut at the corners of the openings ?<br>

  • Add media

  • 10. Were insulation boards additionally fixed to the substrate with proper number of mechanical fixings?<br><br>

  • Add media

  • 11. Has the wall been checked for straightness before mesh was applied?<br><br>

  • Add media

  • 12. Has mesh been properly overlapped at joints?<br><br>

  • Add media

  • 13. Has the mesh been lapped over the top of the wall?<br><br>

  • Add media

  • 14. Have additional mesh reinforcement pieces been added to the insulation surface at four corners of the openings?<br><br>

  • Add media

  • 15. Have two number of base coat been applied and sponged ?<br><br><br>

  • Add media

  • 16. Has all protection been done?<br><br><br>

  • Add media

  • 17. Is the wall suitable for application of the final coat? (Weather forecast must be checked before application)<br><br><br>

  • Add media

  • 18. Is wall dry and free from bumps and hollows before application of Final coat?( must be checked with 2m straight edge)<br><br>

  • Add media

Insulated render/final coat

  • 1.Have colours of the final coat been confirmed ? Were drawings checked so as to make sure that proper colour of final coat has been applied?<br><br><br>

  • Add media

  • 2. Was specified primer applied evenly to the surface of reveals and walls?<br>

  • Add media

  • 3. Was final coat applied during suitable weather condition as specified by manufacturer?<br>

  • Add media

  • 4. Is the texture and colour of render consistent?<br>

  • Add media

  • 5. Were curing conditions maintained?<br>

  • Add media

  • 6. Were elements adjoined to render including: trims, sills, construction joints, opening frames, soffits, cappings etc. secured from dirt of adhesive, paints and top coat?<br>

  • Add media

  • 7. Has work area been left clean on completion?<br>

  • Add media

Capping.

  • 1. Has parapet wall been sealed properly with roofing membrane/Tyvek membrane.?<br>

  • Add media

  • 2. Have brackets been fitted with correct fixings and supported to prevent deforming / bowing to achieve a tight seal with the underside of the capping ?<br>

  • Add media

  • 3. Have proper seals been fitted to brackets to prevent any moisture penetration?<br>

  • Add media

  • 4. Have cappings been fitted to the brackets with correct fixings and at correct centres?

  • Add media

  • 5. Have capping been fitted evenly and to required level.?<br><br>

  • Add media

  • 6. Has Spray-bar test been arranged at required point in installation ?

  • Site notes.

  • Add media

  • Add signature

  • Add signature

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.