Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Final checks.

  • Have you gas tested for a minimum of five minutes?

  • Is the gas meter located to satisfy all clearance requirements?

  • Is there an LPG bottle set up on this property, and if so, have all clearances been met?

  • Mini Taps installed to all fixtures?

  • Fridge Tap installed with Washing Machine Tap?

  • Loxceal to be used on male thread only!

  • Has all tapware and toilets been fitted and free from scratches, dints or any other imperfection?

  • Has all excess silicone around base of toilets, basins and plug & washers been removed and cleaned to leave a neat finish?

  • Have all pan screws and guards been fitted?

  • Have all required holes been drilled for the dishwasher?

  • Does the sink waste have a nipple that the dishwasher can connect to?

  • Dishwasher installed level and tested?

  • Is the HWS installed and commissioned?

  • Have all valves been installed including Tempering Valve, Cold Water Expansion and Duo/NRV Valve

  • HWS positioned on approved base with overflow, PTR and Cold Water Expansion valves discharged over grate/tundish

  • All pipes and valves insulated with UV stable lagging including Cold Water Expansion, Tempering Valve and 500mm minimum cold water pipe to hot water unit

  • Have you tested and confirmed that there are no cross connections?

  • Have all fixtures been tested thoroughly and checked for leaks?

  • All pipe work that passes through cabinets & shelves have cover plates been installed to cover all holes?

  • Are all PVC pipes and plastic traps used for waste connections clean and free of excessive marks and dirt?

  • Is there a 500kpa boundary limiting valve fitted to the water meter?

  • Have the solar panels been installed and the flow and return lines connected?

  • Has the Boundary Riser Shaft been capped and concrete cover fitted at ground level?

  • Is the ORG charged correctly and at least 150mm below the lowest fixture and 75mm above finished ground level?

  • Where a boundary trap is installed, is there a multi vent fitted?

  • Is the boundary trap vent at least 3m away from an openable window?

  • Are the vents through the roof and complete with Dectite, Apron and Vent Cowl.

  • Has the stormwater overflow been fitted off with a finishing collar and flat grate at ground level?

  • Stormwater connected to kerb?

  • Are all downpipes and droppers completed with all clips installed?

  • Have all Hose Taps been fitted with Vacuum Breakers?

  • Have you checked the plans & job specifications for any extra inclusions?

  • Has all rubbish been picked up, placed in a bin provided and secured so it does not blow away?

  • Have all external windows and doors been locked?

  • Has the site been left in a safe state with all site fences closed?

  • Notes-

  • Add media

  • Is this job ready for the next stage?

  • I have checked all the above items and the work has been done to a satisfactory standard.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.