Title Page
-
Job Number
-
Client / Site
-
Conducted on
-
Site Address
-
Checked By
-
Signed By
-
GJ Job Number
Foundation Checklist Number 2
-
Consent Number
-
Site Conditions
-
LBP License Holder Name
-
LBP Number
-
Has Work Been Completed In Accordance With Approved Plans
-
Minor Variations (AC2131) Inspection May Proceed. Documentation Received
-
Has Form AC2131 Been Completed
- Yes
- No (If No Inspection Has Failed)
-
Amendment: Inspection May Only Proceed if Building Work Does Not Affect This Inspection. Formal Amendment Required.
-
CoW Required From Designer ?
-
Does The Amendment Affect This Inspection ?
-
RoW Required From Contractor ?
-
If Yes Can Inspection Proceed ?
Inspection Results
-
Pass Denotes This Inspection Is In Accordance With The Building Consent & Building Code. (Work Can Proceed.)
-
Fail (Denotes This Inspection Is Not In Accordance With The Building Consent & Building Code. (Re-inspection Is Required.)
-
IF The Inspection Fails, Please Issue a Site Instruction & Record Number
General
-
Are Consented Plans Sighted ?
-
All Previous Inspections Approved ?
-
Any Other Site Issues (Comments)
-
Is Inspection For Correct Consent ?
-
Any Applicable Conditions/advise Notes ?
-
Any Existing Damage To Footpath, Crossing, Berm ?
- Yes (Take Photos of Existing Damage)
- No
-
Insert Photos Here.
Documentation
Producer Statement Required For:
-
Geotechnical (PS4)
-
Drain Bridging / Piles (PS4)
-
Pile driving ( PS4)
-
Footings (PS4)
-
Retaining Walls (PS4)
-
Excavation Near Boundary (PS4)
Surveyors Certificates Required For:
-
Siting (Set Out)
-
Floor Level
-
Concrete Docket Required
-
Site Observations Required
-
Height In Relation To Boundary
-
DOSLI Or LINZ Datum
-
EPA Notification (Advice Notes)
-
Silt & Erosion Controls In Place
-
Please Insert Photos
-
Consent Number
-
Date:
-
Documentation Comments
Foundations
-
Siting (Boundaries). Checked
-
Datum Heights Checked
-
Underground Services (Existing)
-
Bridging Of Drains (As Per Spec Designs)
-
Bearing Capacity
-
Reinforcing Bars Tied & Supported
-
Anchor - Brace - Point Load Piles
-
Site Contours
-
Footprint Layout Checked
-
Underground Services (New)
-
Height Pegs Placed
-
DPM Lapped & Taped
-
Pile Treatment
-
Foundation Depth And Width (In mm)
-
Pass
-
Fail
-
N/A
-
Reinforcing Steel Clearance (In mm)
-
Pass
-
Fail
-
N/A
-
Starter Steel Reinforcing (Size / Spacing) (In mm)
-
Pass
-
Fail
-
N/A
-
Pile Hole Diameters and Depth (In mm)
-
Pass
-
Fail
-
N/A
-
Timber Pile / Pole Size (In mm)
-
Pass
-
Fail
-
N/A