Title Page
-
Select the template title
- 050A- HS-002 Construction Site Inspection
-
Client / Site
-
Conducted on
-
Inspected by
-
Position
-
General Description Of Construction Site Activities
-
Number Of Contractors On Site
-
Address
Information
-
Equipment
-
Voltage
-
Site Contact
-
Company
-
Tel No.
Section (A) Main Construction Site - Office Checklist
-
1.0 Is the Edina Project SHEQ File on Site
-
1.1 Is there evidence of a Permit-To-Work System being used
-
1.2 Is the F10 (Or equivalent) displayed in the main site office
-
1.3 Is there a Health & Safety Law poster displayed on site
-
1.4 Are the current Edina employer's liability insurance details displayed on site
-
1.5 Are the current client's employer's liability insurance details displayed on site
-
1.6 Is the location of the nearest Hospital A&E displayed on site
-
1.7 Is the accident book on site
-
1.8 Have any entries into the accident book been removed and given to the SHEQ Department
-
1.9 Is there a method of raising an alarm in the event of a fire
-
2.0 Are there suitable fire extinguishers in the main office
-
2.1 Have the fire extinguishers been inspected within the last 12 months
-
2.2 Is there a fire risk assessment displayed in the main construction site office
-
2.3 Is the Edina Site Managers 1st Aid at Work certificate displayed on site
-
2.4 Is the 1st aid kit on site
-
2.5 Is the 1st aid kit correctly stocked
-
2.6 Is the name of the 1st aid appointed person(s) displayed in the main construction site office
-
2.7 Is there an eye wash station on site
-
2.8 Is the eye wash station correctly stocked
-
2.9 Is there an Edina sign in book on site
-
3.0 Is there evidence of a site induction's taking place
-
3.1 Is there evidence of contractors trade cards being recorded
-
3.2 Have the contractors RAMS been correctly stored on site for the activities currently taking place
-
3.3 Have the contractors RAMS been reviewed by the Edina Site Manager
-
Conclusions & Recommendations
Section (B) Main Construction Site - Compound
-
3.4 Has the site compound been secured with suitable fencing
-
3.5 Has the site fencing been identified with Mandatory construction site signage
-
3.6 Has an Edina sign been place at a prominent position at the site entrance when Edina are the PC
-
3.7 Can the site entrance be secured at night or when not in use
-
3.8 Is there a muster point sign on display
-
3.9 Is there suitable space for contractor vehicle parking
-
4.0 Can reverse parking be used
-
4.1 Is the compound tidy and free from litter
-
4.2 Is the site skip correctly used
-
4.3 Does the site have pedestrian walkways
-
4.4 Are pedestrian access routes protected by barriers
-
Conclusions & Recomendations
Section (C) Main Construction Site - Welfare Facilities
-
4.5 Are the on site toilet facilities suitable for the number of contractors present
-
4.6 Are the toilets clean and tidy
-
4.7 Are there an adequate number of sinks for handwashing
-
4.8 Are there adequate soap facilities for handwashing
-
4.9 Are there adequate paper towel's in the toilets
-
5.0 Are there adequate paper towel storage bins
-
5.1 Is drinking water available on site
-
5.2 Is there a mess room on the site
-
5.3 Does this have the facility to heat food and prepare hot drinks
-
5.4 Is there a drying room on site
-
Conclusions & Recommendations
Section (D) Main Construction Site On Site Scaffolding Towers
-
5.5 Are scaffolds erected and dismantled by a competent person
-
5.5 Is there evidence of relevant trade cards for the scaffolder's in the main office
-
5.6 Does the scaffold display an in date SCAFFTAG
-
5.7 Are all uprights provided with base plates
-
5.8 Are the uprights, ledgers, braces and struts in position
-
5.5 Is the scaffold secured to the building or structure
-
5.6 Are all toe boards in place and secure
-
Conclusions & Recommendations
Section (E) Main Construction Site - Ladder Access
-
5.7 Are the ladders on site class 1 Industrial - BS EN 131
-
5.8 Do the ladders have a ladder tag attached to them
-
5.9 Have all the ladders on site been recorded in the site ladder register
-
6.0 Do ladders that are used to access a platform rise 1 meter above that platform
-
Conclusions & Recommendations
Section (F) Main Construction Site - Roof work - Edina ISO Containers
-
6.1 If high level work taking place is there adequate edge protection
-
6.2 Have fragile roof's been identified
-
6.3 If contractors are working at height do they have suitable training
-
6.4 Are safety harnesses being used on site
-
6.5 Does the Edina Site Manager have a copy of any harness test and inspection certificate (6 monthly L.O.L..E.R)
-
6.6 Is a safety line system currently in use
-
Conclusions & Recommendations
Section (G) Main Construction Site - On Site Excavations
-
6.7 Is there adequate support for any on site excavations
-
6.8 Have excavations been sloped back or battered back to a safe angle
-
6.9 Is there safe access and egress to the excavation
-
7.0 Are all on site excavations correctly fenced off
-
7.1 Do all fences have the correct mandatory H&S warning signs
-
Conclusions & Recommendations
Section (H) Main Construction Site - Manual Handling
-
7.2 Are there materials that require manual handling
-
7.3 Are the contractors using the correct PPE for manual handling
-
7.4 Do the contractors have any certificate of training for manual handling
-
Conclusions & Recommendations
Section (I) Main Construction Site - Traffic, vehicle & Plant Movements
-
7.5 Are vehicles pedestrians adequately segregated
-
7.6 Are vehicles and plant correctly maintained
-
7.7 Are traffic routes correctly identified
-
7.8 Is there a traffic management plan on site
-
Conclusions & Recommendations
Section (J) Main Construction Site - Tools & Machinery
-
7.9 Are the correct tools being used for the job
-
8.0 Do all dangerous parts have suitable guards in place
-
8.1 Are all machinery e-stops fitted and working
-
Conclusions & Recommendations
Section (K) Main Construction Site - Powered Access Equipment (M.E.W.P's)
-
8.2 Are the MEWP operators trained and competent
-
8.3 Is there a copy of the IPAF licence in the main construction site office
-
8.4 Does the equipment have suitable guard rails and clip on points
-
8.5 Has the equipment been inspected by a competent person
-
8.6 Are operators wearing a safety harness when required
-
Conclusions & Recommendations
Section (L) Main Construction Site - Cranes
-
8.7 Is there a lifting plan for the works in place
-
8.8 Are all operator certificates available
-
8.9 Has the area been cordoned off to prevent people walking under the lift area
-
9.0 Does all the equipment used for lifting have an in date certificate of though inspection
-
Conclusions & Recommendations
Section (M) Main Construction Site - Fire & Emergency Procedures
-
9.1 Have emergency procedures been identified in the Construction Site Induction
-
9.2 Is there a fire bell on site
-
9.3 Is there an emergency air horn on site
-
9.4 Are flammable materials stored on site
-
9.5 Are flammable materials stored in minimal quantities
-
9.6 Are any gas cylinders stored on site
-
9.7 Is smoking banned on site
-
9.8 Do contractors have fire extinguishers when required by there RAMS for hot works
-
Conclusions & Recommendations
Section (N) Main Construction Site - Control of Substances Hazardous to Health (COSHH)
-
9.9 Do all substances that contractors bring onto site have a MSDS (Material Safety Data Sheet)
-
10.0 Do all substances that contractors bring onto site have a suitable and sufficient risk assessment
-
10.1 Are the contractors wearing the correct PPE as identified in the risk assessments
-
10.2 Are staff aware that any spillage must be reported
-
10.3 Is there an emergency spill kit on site
-
10.4 Is the emergency spill kit correctly stocked
-
Conclusions & Recommendations
Section (O) Main Construction Site - Essential Services (Electrical - Gas - Water)
-
10.5 Are cabin distribution boards C/W NICEIC test date
-
10.6 Has the location of electrical services been identified
-
10.7 Has the location of gas services been identified
-
10.8 Has the location of water services been identified
-
10.9 Is all equipment in the main office PAT tested
-
11.0 Is this equipment listed on a PAT test register
-
Conclusions & Recommendations
Section (P) Construction SHEQ Site Inspection Acceptance
-
The above Construction SHEQ Site Inspection has been carried out by a member of the SHEQ Dept. and hereby submitted to the appropriate Department Line Manager for follow-up and closure of the corrective actions as detailed above.
-
Inspector (Name and Signature)