Title Page
-
Site conducted
-
Inspection conducted
- 122-SD-000 - Service Site Inspection
-
Client / Site
-
Conducted on
-
Inspected by
-
Position
-
Address
Information
-
Equipment
-
Voltage
-
Site Contact
-
Company
-
Tel No.
Section (1) Site Conditions
-
"Please take photographs to highlight areas that do not meet the required standard or show an example of good site conditions"
-
1.0 Is there adequate site stock in place
-
1.1 Is the site clean & tidy
-
1.2 Is there adequate provision for waste removal
-
1.3 Is the site defect free
-
1.4 Is the CHP free from leaks
-
1.5 Is the Edina Log Book on-site
-
1.6 Is the Edina Log Book correctly filled in
-
1.7 Is the site security system operating correctly (STOR only) if CHP site please indicate N/A
-
1.8 Is there site access to double doors (STOR only) if CHP site please indicate N/A
-
Conclusions & Recommendations
Section (2) Health & Safety
-
2.0 Is the correct signage in place
-
2.1 Is the step height into the container acceptable (less than 300mm)
-
2.2 Are the underfoot conditions acceptable
-
2.3 is there correct engine ventilation in place
-
2.4 Is there correct ventilation in place for electrical cabinets
-
2.5 Are portable electrical items within PAT test date
-
2.6 Are the ladder guards on site
-
2.7 Are the ladder guards correctly fitted
-
2.8 Is there adequate site lighting
-
2.9 Are all the lights in the container operational
-
3.0 Is the fire alarm within test date
-
3.1 Has the Fire log book been completed (STOR Only) if CHP please indicate N/A
-
3.2 Is the gas alarm within test date
-
3.3 Are the gas alarm calibration certs on site
-
3.4 Is the emergency lighting operational
-
3.5 Are all the door handles functional
-
3.6 Are all the door locks functional
-
3.7 Are all the flywheel guards in place
-
3.8 Are all the flywheel guards in good condition
-
3.9 Is the lagging for high temperature surfaces in place
-
4.0 Is the lagging for high temperature surfaces in good order
-
4.1 Is there evidence that the Engineer has been correctly inducted onto a Welsh Power Site (If non Welsh Power Site please indicate N/A)
-
Conclusions & Recommendations
Section (3) Engineer
-
4.2 Is the site responsible engineer up to date with all online training
-
4.3 Is the work being carried out to the expected level
-
4.4 Is the correct PPE being worn
-
4.5 Are all service records up to date
-
4.6 Have all outstanding issues with the engine been addressed
-
4.7 Is engine availability maintained to the correct level
-
4.8 Is the responsible site Engineer implementing first time fixes
-
4.9 Is paper work submitted in a timely manner
-
5.0 Has the site Engineer completed the gas safe assessment
-
Conclusions & Recommendations
Section (4) Engine & Installation
-
5.1 Is the engine maintaining demand set point
-
5.2 Are there any de-rates identified
-
5.3 Are all the 3-way valves below 100%
-
5.4 Have all leaks been rectified
-
5.5 Is the engine in good condition
-
"Please answer the next questions regarding parts with Yes if all parts have been returned, and with no if there are parts on site to be returned, please ensure photographs are obtained for all items that require removal"
-
5.6 Have all used cylinder heads been returned to Edina
-
5.7 Have all used starter motors been returned to Edina
-
5.8 Have all ignition boxes been returned to Edina
-
5.9 Have all actuators been returned to Edina
-
6.0 Have all governors been returned to Edina
-
6.1 Is the room engine clean and tidy
-
6.2 Is the control room clean and tidy
-
6.3 Is the cable entry run into the control room adequately sealed
-
6.4 Are the coolant compensators in good condition
-
6.5 Are the dump radiators in good condition
-
6.6 Are engine guards in place
-
6.7 Are all alternator guards in place
-
6.8 Are all protective guards in good condition
-
6.9 Has the ZPR Protective cover been fitted
-
7.0 Is the SHEQ File on site
-
7.1 Is a QR Code available on site
-
7.2 Is there an up to date version of the SHEQ File on SharePoint
-
7.3 Is the P&ID available on site
-
7.4 Is the P&ID available electronically
-
7.5 Are the electrical drawing available on site
-
7.6 Are the electrical drawings available on Sharepoint
-
7.7 Is the LOTO correctly displayed
-
7.8 Is the LOTO correctly stocked
-
7.9 Is the gas analyser functioning correctly
-
8.0 Is the gas analyser service in date
-
8.1 Is the condensate drain on the silencer operational
-
Conclusions & Recommendations
-
The above Site Inspection has been carried out by a member of the Service Dept. and hereby submitted to the appropriate Department Line Manager for follow-up and closure of the corrective actions as detailed.
-
Senior Engineer (Name & Signature)
-
Engineer (Name & Signature