Site General Conditions

  • Is it a Leasehold or Freehold property?

  • Is it a Listed Building?

  • Is it within a Conservation Area?

  • Has Planning Permission been achieved?

  • Has Listed Building Consent been achieved?

  • Are there any planning restrictions?

  • Has Licensing been achieved?

  • Has a pavement licence been applied for?

  • Is change of use required?

  • Has asbestos survey been carried out yet?

  • Is Landlord Permission required?

  • Is a license to alter required?

  • Is this a developers shell?

  • Are any Rights of Ways required?

  • Does anyone have any access rights over our demise?

  • Have we got an agreed customer occupancy figure?

Architects Report

  • Brief outline of proposals to development team completed?

  • Comments on design proposal recieved?

Site External Questions

  • Have site boundaries and demise been established?

  • Have delivery routes been established?

  • Has main customer entrance been established?

  • Has a DDA level access route been established?

  • Have Fire Escapes been identified?

  • Does the site offer a beer garden or external drinking / smoking area?

  • Has a covered area externally been identified?

  • Has a bin store been identified?

  • Has a plant position been identified?

Building Dilapidations

  • Has existing building been cleared ? ( allowance of 1x 8yd skip can remain )

  • Are any items internally to be retained for use within new scheme? ( including furniture, kitchen equip, cellar equip )

  • Roof condition

  • External walls condition

  • External joinery condition

  • Rainwater goods condition

Internal Considerations

  • Is opening shop front possible?

  • Are opening windows possible?

  • Can we add any further natural daylight opportunities?

  • Can we achieve an open kitchen?

  • Can we achieve an open cellar?

  • Will we achieve a well defined Vertical Drinking Area?

  • Will we have adequate fire escapes?

Positions Discussed and Agreed as Best Position

  • Bar Servary

  • Wash Up

  • Kitchen

  • Fridge and Freezer

  • Cellar

  • Cooled bottle store

  • Wine and Spirit Store

  • Ladies and Gents WC's

  • Cleaners Cupboard

  • Disabled WC

  • Office (check for safe cash route)

  • Staff Room

  • Staff WC

  • Plant Room

  • Storage Rooms

  • AWP Positions

  • Plasma / Drop Down Screen Positions

  • Solid Fuel fire

  • Lift or Ramp positions

Services

  • Is Gas upgrade required?

  • Is Water upgrade required?

  • Report on existing mechanical equipment and any likely issues for scheme.

  • Is Electric upgrade required?

  • Report on existing electrical equipment and any likely issues for scheme.

  • Is there BT lines on site?

  • Will wet heating system be used?

  • Will AC be used?

  • Are we able to incorporate Loznay heat recovery units?

  • Have Air In ducting routes been agreed?

  • Have Air Extract positions been agreed?

  • Has Kitchen Extract ducting route been agreed?

  • Is kitchen filtration required?

  • Has future Maintenance been concidared?

  • Are there any unusual maintenance requirements? ( such as access equipment, permissions, frequency )

  • Has all Mechanical and Electrical related information needed for Planning or Listed consents been submitted?

CDM-Co-Ordinators Report

  • Will project be more than 30 days or 500 person days on site?

  • Will F10 notification be required?

  • Does CDM-C have any concerns over project program?

  • Is there any Asbestos information currently available?

  • Will a full Refurbishment and Demolition asbestos survey be required?

  • Will any specialist surveys be required? ( Such as soils, archeology, arboricultural, dilapidation, structural, historical )

  • Has date for passing all Design Risk assessment information to Architect and CDM-C been agreed?

  • Has CDM-C got any comments on DDA or Access issues?

Structural Engineers Report

  • Does the Structural Engineer have any concerns of existing building condition?

  • Is Structural Engineers advise required for proposed scheme?

  • Has a deadline for structural information required for design and pricing been agreed?

Kitchen Contractors Report

  • Is the proposed area for the kitchen deemed acceptable?

  • Will a standard JDW kitchen specification fit within the space allocated?

  • Has the delivery route been established and agreed as acceptable?

  • Is there any concerns regarding kitchen position and space allowed?

Innserve

  • Is the proposed area for the cellar deemed acceptable?

  • Has the delivery route been established and agreed as acceptable?

  • Will DHL need to carry out a detailed visit to ensure deliveries can be made effectively?

  • Is there any concerns regarding cellar position and space allowed?

Secom

  • Has site visit highlighted any additional security risks that need consideration?

  • Will site have full CCTV coverage within trade area?

  • Will external areas have full CCTV coverage?

  • Has smoke screen position been agreed?

Lift Engineer

  • Does the property have any existing lift equipment that can be used?

  • Is a lift or hoist required?

  • Has a position for lift shaft and pit been agreed?

  • Does the lift shaft or pit have any special requirements?

Draft Development Programme Dates

  • Number of weeks on site agreed

  • Date agreed for full issue of design information pack for pricing ( including any redesigned items )

  • Date agreed for full costed scheme to be returned to Architect

  • Date agreed for JDW cost approval pack to be submitted? ( including Tom Lucas feedback )

  • Asbestos survey date agreed?

  • Has an anticipated Start On Site date been agreed?

  • Initial SOS, BC, and HO dates. ( These may change as more information becomes available )

Sign Off

  • In PDM's opinion is this a well considered scheme?

  • Has the Architect got clear instructions on any changes made during meeting?

  • Have all members of the team got enough information to provide accurate pricing that will not vary at contract stage?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.