1.0 - Screw centres.
-
1.1 - Boards screwed up @ 300mm centres
-
1.2 - Door jambs screwed up @ 200mm centres
-
1.3 - External corners screwed up @ 200mm centres
-
1.3 - Screws not too proud or sunk too deep
2.0 - Studs
-
2.1 - Studs set out correctly
-
2.2 - Studs @ correct deflection
-
2.3 - Party wall studs in place and braced
-
2.4 - Sacrificial walls studs in place
3.0 - Boards
-
3.1 - Boards @ correct deflection
-
3.2 - Door edges and external corners surfed
-
3.3 - Correct type of boards used
4.0 - Flat plate
-
4.1 - Flat plate @ correct height
-
4.2 - Flat plate tek screwed to studs correctly
-
4.3 - Flat plate screwed up through boards
-
4.4 - No joins in between studs
5.0 - Mastic
-
5.1 - Mastic bead applied to core board
-
5.2 - Mastic bead applied to floor track
-
5.3 - Mastic bead applied to abutment studs to columns
6.0 - Setting out
-
6.1 - Walls set out correctly as per architect's drawings
-
6.2 - Fire compartment maintained
7.0 - Letterbox
-
7.1 - Letterbox formed correctly
-
7.2 - Letterbox lined with plasterboard
-
7.3 - Letterbox cut out
8.0 - Waste
-
8.1 - Debris and waste cleared out
-
8.2 - Plot swept out
-
8.3 - No Boxes of screws and other consumables left in plot
Sign Off
-
Select date
-
signature