Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Those present at Meeting

  • Enter Details of all Persons Present at Meeting

Architects Report and Site Specific Reminders

  • Has Architect rebriefed project, highlighting any changes from original briefing meeting?

  • Is it a Leasehold or Freehold property?

  • Is it a Listed Building?

  • Is it within a Conservation Area?

  • Has Planning Permission been achieved?

  • Have all planning conditions been discharged?

  • Has Listed Building Consent been achieved?

  • Are there any planning restrictions, hours, noise etc?

  • Has Licensing been achieved?

  • Has a pavement licence been applied for?

  • Has landlord permission been achieved?

  • Has a license to alter been received?

  • Has signage scheme been formally approved, and issued to all parties?

  • Any development shell issues?

  • Confirm Rights of Ways as applicable?

  • Does anyone have any access rights over our demise?

  • Are party wall awards applicable and if applicable have they been agreed?

  • Are timber or damp specialist reports required?

  • Have full sets of all drawings been issued to all members of the development team?

  • Has a finishing schedule been issued to clarify all details?

  • Has the green PCF been signed?

  • Detail revision/ option number

  • Has a cost tracking document been prepared and ready for issue on week one of contract?

  • Have site access arrangements been agreed with Main Contractor?

  • Has Architect confirmed the design team responsible for the project with contact details for all parties?

  • Have promotional boards for new development been arranged for nearest JDW sites?

  • Have operations team been sent the briefing pack?

  • Has formal JDW operations team feedback been received on AWP positions?

  • Has the day and dates of progress meetings been agreed with development team?

  • Have JDW given formal approval of project dates and agreed with Letter Of Approval or Email?

  • Have valuation of works procedures been agreed?

  • Has Client Direct list or orders and descriptions been issued to Main Contractor?

  • Are there any outstanding Client Direct orders or items?

  • Is there a Global Fire Fighting equipment design issued?

  • Has the staff facilities layout been approved at the Design meeting?

  • Has the Development information to ops been prepared including DHL plan?

  • Has Biffa been contacted to arrange a site survey?

Main Contractor

  • Has program been issued to all parties?

  • Do all parties agree that the program is realistic and achievable?

  • Has a Information Required List been issued, and a date for answers agreed upon with all parties?

  • Has location of site office and welfare facilities been agreed?

  • Have arrangements been agreed for site access / security, and signing in and out procedures?

  • Has there been confirmation of PPE requirements for the site?

  • Have working hours been discussed and agreed upon?

  • Have any delivery restrictions been discussed and agreed upon?

  • Have pavement licence, skip license, highway blockage etc been applied for?

  • Have Site Agents and Contract Managers details been circulated to all?

  • Has Building Inspector been notified of start on site dates?

  • Are there any materials chosen that cause concern due to suitability or availability ?

  • AOB - Main Contractor

Contract Documents

  • Has Work Instruction been signed by Property Development Manager and Main Contractor?

  • Have project preliminaries been attached to the Works Instruction?

  • Has Mechanical Collateral Warrenty been signed by Property Development Manager, Mechanical Contractor and Main Contractor?

  • Has Electrical Collateral Warrenty been signed by Property Development Manager, Electrical Contractor and Main Contractor?

  • Have Work Instruction, Project Preliminaries, Mechanical Collateral Warranty and Electrical Collateral Warranty been emailed to JDW head office?

CDM Co-Ordinator

  • Have we got an agreed customer occupancy figure that both architect and CDM-C agree with?

  • Has F10 been signed and issued?

  • Has Construction Phase Health and Safety plan been approved?

  • Has asbestos survey been carried out and all asbestos removed from site?

  • Has a clean air certificate been issued if applicable?

  • Has a Permit to Proceed been issued?

  • Are there any work items that present unusual risks?

  • Are all Risk Assessments and Method Statements on file adequate and accurately describe the works to be undertaken?

Structural Engineer

  • Does the Structural Engineer have any concerns of existing building condition?

  • Have all necessary structural drawings been issued?

  • Has a time for all opening up / demolition works been agreed for checking?

Mechanical Contractor

  • Has all redundant pipe work and ducting been identified for strip out?

  • Have contract drawings been issued, and match Architects layouts?

  • Have upgrades to Water and Gas been carried out, or at least programmed in within contract period?

  • Have access requirements to plant equipment been identified and discussed?

  • Will customer staircase / corridor areas be adequately heated?

  • BWIC to be marked up and issued to Main Contractor in week 2

  • Is plant in the position agreed at Briefing meeting?

  • AOB - Mechanical Contractor

Electrical Contractor

  • Have all redundant cables been identified for strip out?

  • Has upgrade to Electrics been carried out, or at least programmed in within contract period?

  • Have lighting layout drawings been recieved?

  • Are light fittings style and weights fully understood?

  • Has delivery date for lights been agreed, and a safe place identified on site for storage?

  • Do all external doors have over door heaters?

  • Does staff area, office and back of house corridors have adequate panel heaters?

  • Will all external lights be on Dusk until Dawn sensors?

  • Are all lamps to be LED supplied from Mico?

  • AOB - Electrical Contractor

Kitchen Contractors Report

  • Will all existing kitchen equipment be stripped out on a date agreed?

  • Are any pieces of equipment salvageable for re-use?

  • Has a DAG approved kitchen layout been issued?

  • Plan number

  • Has a DAG approved Wash Up area drawing been issued?

  • Has a delivery date for kitchen equipment to site been agreed?

Innserve

  • Will all existing cellar equipment be stripped out on a date agreed?

  • Are any pieces of equipment salvageable for re-use?

  • Has a cellar layout drawing been issued?

  • Is the Free Air system incorporated into design?

  • Are Innserve happy with the location of the condensers and that they will work as designed with no issues?

Secom

  • Has second site visit highlighted any additional security risks that need consideration?

  • Will site have full CCTV coverage within trade area?

  • Will external areas have full CCTV coverage?

  • Has smoke screen position been agreed?

  • Is lighting layout understood and confirmed as not conflicting with camera layout?

  • Is there any developments in technology we should consider to improve this sites security?

  • Confirm that the fire alarm will be connected to the alarm signalling line?

Lift Engineer

  • Does the property have any existing lift equipment that can be used?

  • Has a position for lift shaft and pit been agreed?

  • Does the lift shaft or pit have any special requirements?

  • Are first and second fix dates agreed with the Main Contractor?

Development Programme Dates Agreed

  • Start on Site

  • Builders Completion

  • Handover

  • PO1

  • PO2

  • 6 Months Defect Meeting

Sign Off

  • Is Architect happy to start project and deliver it on time and within budget?

  • Is Main Contractor happy to start project and deliver it on time and within original contract sums?

  • Is Mechanical Contractor happy to start project and deliver it on time and within original contract sums?

  • Is Electrical Contractor happy to start project and deliver it on time and within original contract sums?

  • Is PDM happy to start project and confident there is enough information to complete the project on time / budget?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.