Title Page
-
Document Number
-
Materials Number
-
Materials Name
-
Conducted on
-
Prepared by
-
Level (xx)
-
Location
-
Document Number (xxx)
-
Location:
E1 - Elevation 1; E2 - Elevation 2 ……
H1 - Hoist 1; H2 - Hoist 2 ……
S1 - Shear Wall / Stair 01; S2 - Shear Wall / Stair 02 ……
B1 - Balcony 1; B2 - Balcony 2 ......
P1- Plot 1; P2 - Plot 2 ……
Signatures
-
Installation Company
-
Name
-
Signature
-
Lingyun Representative
-
Name
-
Signature
-
OSHEA Representative *optional
-
Name
-
Signature
Control & Check
-
Sika EPDM Membrane 0.6mm sealed with the base profiles, refer to Upstand Inspection Report' for the specific location. Photos are to be taken for the record.
-
Mineral insulation 60kg/m3 packed on top of the EPDM Membrane and filling all gaps between the base profiles and the aluminium copings, Photos are to be taken for the record.
-
Aluminium copings installed as per drawing: 19mm gap between panels; foam rod fixed in the gaps between panels; sika silicone sealing coverings all gaps,Photos are to be taken for the record.
-
Aluminium copings fixed with screws ,intervals are as per drawing,Photos are to be taken for the record.
-
Any other Comments/Remarks?